Seven of the eight steps already have their data in RunResult and need a print;
one does not exist at all. Putting that distinction in a table is the point of
this plan -- it turns "show all eight steps" from an unbounded week into one
build on Friday and presentation work over the weekend.
The go/no-go on Tuesday is deliberate. The content is being built in another
repo on a deadline nobody here controls, so the week is designed to survive it
not arriving rather than to hope it does. The content-keyed reply selector
lands Monday, before the content, for the same reason: a new project should
then be a data entry rather than a hand-written script under time pressure.
Honesty framing is section 1 rather than a footnote, because the demo's own
subject is a system that refuses to claim more than it proves.