docs(rapport): corrections after the second fresh-reader test (round 9e)
Four new readers, each with a controller, read the corrected PDFs, the carousel, the post and the text of the results page. No measured number was wrong. The summaries, chapters 6, 8 and 10 and the results page now say that twelve years from decision to grid applies to the Emirates only, that a full yes was in practice out of reach, that the first-year cash flow is a year without chip purchases, where the cost range for nuclear power comes from and what the committee behind it concluded, that the study behind the dedicated plant found the grid as backup cheaper, and what the cooling water and emission columns on the results page are. The source bank counts 1,237 entries. PDFs rebuilt (171 and 2 pages); the results page rebuilt (7,213 numbers). The carousel is not part of this commit. Co-Authored-By: Claude Fable 5.2 <noreply@anthropic.com>
This commit is contained in:
parent
b5ce07e0b6
commit
502cdaa550
13 changed files with 178 additions and 127 deletions
|
|
@ -7,10 +7,13 @@
|
|||
\paragraph{Svaret}
|
||||
\textbf{Hypotesen holder ikke.} Statlig eide AI-datasentre som eksporterer regnekraft, lønner seg ikke for
|
||||
Norge i scenarioet som teller, og de kan ikke bli en inntektskilde slik oljen har vært. Svaret gjelder alle
|
||||
de fem kraftløsningene, og dommen over hypotesen er den samme i alle de seks scenarioene som er regnet. Tapet
|
||||
er størst med eget kjernekraftverk, et kraftverk uten nettforbindelse bygd av mange små reaktorer.
|
||||
Kjernekraft på nettet taper mindre, og ny fornybar kraft minst. Regnekraft som statlig eksportnæring i stor
|
||||
skala, «den nye oljen», bør derfor ikke stå som mål for staten; rådet bygger på et normalt marked. Dette kapitlet
|
||||
de fem kraftløsningene, og dommen over hypotesen er den samme i alle de seks scenarioene som er regnet, men når
|
||||
knappheten varer, av en annen grunn enn tap (under). Tapet er stort med kjernekraft, størst med eget
|
||||
kjernekraftverk, et kraftverk uten nettforbindelse bygd av mange små reaktorer, og mindre med kjernekraft på nettet. Med ny fornybar kraft er det
|
||||
lite: anlegget går i null i medianen hvis prisen på regnekraft er
|
||||
\tall{terskler.pris.C.normalisering.pst-over}~\% høyere. Regnekraft som statlig eksportnæring i stor
|
||||
skala, «den nye oljen», bør derfor ikke stå som mål for staten; rådet bygger på et normalt marked og på
|
||||
markedets avkastningskrav. Dette kapitlet
|
||||
sier hva som bærer svaret, hva som kunne endre det, og hva vi lærte. Tallene og reglene bak står i
|
||||
\cref{sec:resultater}.
|
||||
|
||||
|
|
@ -24,7 +27,10 @@ løsningene. For ett anlegg på 1\,000~MW er medianen \tall{dommer.normalisering
|
|||
med ny fornybar kraft, \tall{dommer.normalisering.t1.B.nnv-median}~mrd.~kr med kjernekraft på nettet og
|
||||
\tall{dommer.normalisering.t1.A.nnv-median}~mrd.~kr med eget kjernekraftverk. Eget kjernekraftverk er i
|
||||
modellen et kraftverk uten nettforbindelse, bygd av mange små reaktorer med reserveenheter, etter oppsettet
|
||||
i en studie fra amerikanske nasjonallaboratorier \kilde{K12-001} (\cref{sec:kraftlosningene}). Med
|
||||
i en studie fra amerikanske nasjonallaboratorier \kilde{K12-001} (\cref{sec:kraftlosningene}). Studien fant
|
||||
selv at én stor reaktor med nettet som reserve var billigere. Kjernekraft på nettet er i
|
||||
modellen nye reaktorer på 1\,000~MW som selger til markedet, så mange at produksjonen i et normalår dekker
|
||||
det datasentrene bruker. Med
|
||||
kjernekraft, eget kraftverk eller på nettet, dekker prisen heller ikke kostnaden for virksomheten: kostnaden
|
||||
per enhet regnekraft er under prisen i \tall{dommer.normalisering.t1.A.m2.andel}~\% av trekningene
|
||||
(\cref{sec:res-dommer}).
|
||||
|
|
@ -50,7 +56,8 @@ inntekt utover vanlig avkastning på kapitalen, nevneren statens kontantstrøm f
|
|||
ligger under grensen i \tall{dommer.normalisering.t1.A.m6.andel-ikke}~\% av trekningene, med alle
|
||||
løsningene. Målt som statens kontantstrøm i første år med stabil drift, samme slags størrelse som
|
||||
oljeinntektene, er ett anlegg i medianen \tall{eierformer.A.kontantstrom.median} til
|
||||
\tall{eierformer.C.kontantstrom.median}~\% av dem. Det tallet trekker ikke fra avkastningen på kapitalen
|
||||
\tall{eierformer.C.kontantstrom.median}~\% av dem. Det er et år uten kjøp av nye brikker; brikkene må
|
||||
kjøpes på nytt hvert tredje til sjuende år. Tallet trekker heller ikke fra avkastningen på kapitalen
|
||||
som er bundet, og er ikke målet som ble satt på forhånd (\cref{sec:res-eierformer}). Flere anlegg løfter
|
||||
ikke bidraget over grensen, og de lar seg ofte ikke bygge: et program på fem anlegg lar seg ikke bygge
|
||||
innen 2100 i
|
||||
|
|
@ -78,8 +85,9 @@ Resultatet er ikke at regnekraft aldri kan lønne seg. Tre ting trekker den andr
|
|||
ligger år fram i tid, større i dagens kroner, og for eget kjernekraftverk veier det tyngre enn at prisen
|
||||
fortsatt bygger på markedets krav; hvor mye hvert ledd gir, er ikke regnet ut med de frosne tallene. Da er
|
||||
bare nåverdien regnet om: prisen på regnekraft bygger fortsatt på markedets avkastningskrav, og skalaen
|
||||
er ikke regnet på nytt. Regnemåten betyr at staten bærer risikoen som markedet ellers tar betalt for; et
|
||||
lavere krav også i markedet ville i modellen gitt lavere pris. At regelen for forretningsdrift i konkurranse med private gjelder her, er
|
||||
er ikke regnet på nytt. Statens rente på 4~\% har påslaget for et prosjekt med
|
||||
vanlig risiko \kilde{K09-003}, mens markedets krav for regnekraft er høyere; et lavere krav også i markedet
|
||||
ville i modellen gitt lavere pris. At regelen for forretningsdrift i konkurranse med private gjelder her, er
|
||||
prosjektets tolkning, og avkastningskravet for regnekraft er en åpen forutsetning. Får bare kraftverket
|
||||
for kjernekraft på nettet et høyere avkastningskrav (rad~4 i \cref{tab:folsomheter}), blir medianen for
|
||||
den løsningen bedre, ikke dårligere: salget betaler ikke tilbake reaktoren, og et tap som ligger år fram i
|
||||
|
|
@ -113,7 +121,9 @@ Resultatet er ikke at regnekraft aldri kan lønne seg. Tre ting trekker den andr
|
|||
vurdering; modellen regner ikke en slik avtale. Trinnvis utbygging gir likevel større tap
|
||||
i modellen i et normalt marked, og verdien av å kunne stoppe underveis er ikke regnet.
|
||||
\item \emph{Kraften først. Eget kjernekraftverk uten nett ga størst tap, kjernekraft på nettet mindre.}
|
||||
Med eget kjernekraftverk er medianen lavest av de fem løsningene, og sammenlignet med samme modell og
|
||||
Kostnadsspennet for kjernekraft er det konsulentene ga Kjernekraftutvalget \kilde{K16-002}, og utvalget fant
|
||||
selv at kjernekraft ikke er samfunnsøkonomisk lønnsomt i Norge med dagens utsikter til kostnader og
|
||||
markedspriser \kilde{K05-005}. Med eget kjernekraftverk er medianen lavest av de fem løsningene, og sammenlignet med samme modell og
|
||||
regler er det best i \tall{karusell.m7.t1.A.alene}~\% av trekningene for ett anlegg, ny fornybar kraft i
|
||||
\tall{karusell.m7.t1.C.alene}~\% (\cref{sec:res-m7}).
|
||||
Sammenligningen gir ingen dom (\cref{sec:m7}): den sier hvor ofte hver er best, og at en løsning er best,
|
||||
|
|
@ -133,10 +143,13 @@ Resultatet er ikke at regnekraft aldri kan lønne seg. Tre ting trekker den andr
|
|||
Forsyningssikkerheten svekkes da i \tall{dommer.normalisering.t1.R.m4.andel-ikke}~\%, per definisjon:
|
||||
«svekkes» betyr svakere enn uten anlegget, uansett hvor lite. Med eget kjernekraftverk holder den per
|
||||
definisjon, fordi verket ikke er koblet til nettet. De andre løsningene er vurdert uten tiltakene som er
|
||||
betalt, og med ny fornybar kraft er den ikke svakere i \tall{dommer.normalisering.t1.C.m4.andel}~\% av
|
||||
trekningene. Miljøkravet holder per definisjon for ny fornybar kraft. For kjernekraft holder det på vilkår,
|
||||
fordi kjernekraften i én av tre kilder ligger over vind på land, 12 mot 11~g CO\textsubscript{2} per kWh
|
||||
(\cref{sec:res-dommer}). Hvor mye ny kraft som kan bygges per år, bør utredes før noe annet.
|
||||
betalt: med ny fornybar kraft er den ikke svakere i \tall{dommer.normalisering.t1.C.m4.andel}~\% av
|
||||
trekningene, med kjernekraft på nettet i \tall{dommer.normalisering.t1.B.m4.andel}~\%. Tallet er lavere med
|
||||
kjernekraft på nettet fordi kravet, slik det ble satt på forhånd, regnes med den største nye enheten ute i
|
||||
den knappeste timen, og den er en hel reaktor på 1\,000~MW; ny fornybar kraft har ingen så store enheter
|
||||
(presisering~4). Miljøkravet holder per definisjon for ny fornybar kraft. For kjernekraft holder det på
|
||||
vilkår, fordi kjernekraften i én av tre kilder ligger 1~g over vind på land, 12 mot 11~g
|
||||
CO\textsubscript{2} per kWh; i de to andre ligger den ikke over (\cref{sec:res-dommer}). Hvor mye ny kraft som kan bygges per år, bør utredes før noe annet.
|
||||
\item \emph{Det tar lang tid.} Trinnvis utbygging i moduler på 100~MW har de første modulene i drift i
|
||||
\tall{tidslinje.dom.TF.median-aar} i medianen. Et helt anlegg på 1\,000~MW er i drift i
|
||||
\tall{tidslinje.dom.C.halv-1000-aar} med ny fornybar kraft og i \tall{tidslinje.dom.A.halv-1000-aar} med
|
||||
|
|
@ -182,15 +195,18 @@ under spennet i modellen, som er 10\,500 til 16\,500~USD/kW uten renter: Olkiluo
|
|||
7\,200 og Saeul~1--2 i Korea på 2\,700~USD/kW (2023-dollar, uten renter) \kilde{K28-008}. Emiratene, et
|
||||
nytt kjernekraftland, bygde Barakah med en finansieringsramme på om lag 4\,400~USD/kW med renter, nominelt
|
||||
\kilde{K03-011}, og fikk første enhet på nettet om lag tolv år etter vedtaket, under nedre grense på 15 år
|
||||
i modellen \kilde{K05-034}; andre nye kjernekraftland har brukt lenger tid \kilde{K05-035, K05-038}. I om
|
||||
lag halvparten av trekningene leses kostnadsspennet for kjernekraft som et budsjett, og en overskridelse
|
||||
legges oppå. Leses det som sluttkostnad i alle trekningene, blir medianen
|
||||
i modellen \kilde{K05-034}; andre nye kjernekraftland har brukt lenger tid \kilde{K05-035, K05-038}. Kildene
|
||||
er uenige om kostnadsspennet for kjernekraft er et budsjett eller en sluttkostnad \kilde{K16-004, K16-014},
|
||||
så i om lag halvparten av trekningene leses det som et budsjett, og en overskridelse legges oppå. Leses det
|
||||
som sluttkostnad i alle trekningene, blir medianen
|
||||
\tall{folsomheter.rad.1.normalisering.A.median}~mrd.~kr med eget kjernekraftverk og
|
||||
\tall{folsomheter.rad.1.normalisering.B.median}~mrd.~kr med kjernekraft på nettet (rad~1 i
|
||||
\cref{tab:folsomheter}). Observasjonene i kildene er ikke regnet inn (\cref{sec:fagmiljoene,sec:begrensninger}).
|
||||
Tre forenklinger trekker i favør av ny fornybar kraft: vannmagasinene som finnes, jevner ut uten kostnad
|
||||
(ny lagring bygges ikke), verdien av vindkraft faller ikke når mye bygges, og en kald uke uten vind er ikke
|
||||
regnet. To trekker mot satsingen med alle løsningene: prisen på regnekraft har ingen renter i datasenterets
|
||||
\tall{folsomheter.rad.1.normalisering.B.median}~mrd.~kr med kjernekraft på nettet, og nåverdien er positiv i
|
||||
henholdsvis \tall{folsomheter.rad.1.normalisering.A.m1-andel} og
|
||||
\tall{folsomheter.rad.1.normalisering.B.m1-andel}~\% av trekningene (rad~1 i \cref{tab:folsomheter}). Observasjonene i kildene er ikke regnet inn (\cref{sec:fagmiljoene,sec:begrensninger}).
|
||||
Fire forenklinger trekker i favør av ny fornybar kraft: vannmagasinene som finnes, jevner ut uten kostnad
|
||||
(ny lagring bygges ikke), verdien av vindkraft faller ikke når mye bygges, en kald uke uten vind er ikke
|
||||
regnet, og vindkraftens inngrep i natur har ingen pris, mens kjernekraftens forventede ulykkeskostnad er
|
||||
regnet med (\cref{sec:ikke-med}). To trekker mot satsingen med alle løsningene: prisen på regnekraft har ingen renter i datasenterets
|
||||
byggetid, mens Norge betaler bygget og de første brikkene før oppstart, og bare Norge kan rammes av stans i
|
||||
leveransene av brikker. Hva Statnetts funksjonskrav for datasentre på nettet koster, er ikke regnet; det
|
||||
trekker i favør av løsningene på nettet. Høyere strømpris regnes som en gevinst for landet så lenge Norge
|
||||
|
|
|
|||
|
|
@ -104,7 +104,8 @@ for B, C, T-F og T-K, og «holder ikke» for R, som bygger ingen ny kraft og sve
|
|||
alle sju. Telleren i M6 er bidraget utover vanlig avkastning på kapitalen, og nevneren er statens netto
|
||||
kontantstrøm fra petroleum. Målt som statens kontantstrøm i første år med stabil drift, samme slags
|
||||
størrelse som nevneren, er ett anlegg i medianen \tall{eierformer.A.kontantstrom.median} til
|
||||
\tall{eierformer.C.kontantstrom.median}~\% av oljeinntektene; det tallet er ikke målet som ble satt på
|
||||
\tall{eierformer.C.kontantstrom.median}~\% av oljeinntektene. Det er et år uten kjøp av nye brikker;
|
||||
brikkene må kjøpes på nytt hvert tredje til sjuende år. Tallet er ikke målet som ble satt på
|
||||
forhånd (\cref{sec:res-eierformer}). I et normalt marked kunne grensen i M6 i praksis ikke nås, fordi
|
||||
prisen er satt lik kostnaden og store programmer ikke rekker å bli bygget (over og
|
||||
\cref{tab:res-stige}). Neiet til hypotesen kommer fra lønnsomheten (M1).
|
||||
|
|
|
|||
|
|
@ -135,8 +135,10 @@ drift.}\label{tab:res-eierformer-kontantstrom}
|
|||
Medianen er positiv for alle fem løsningene, fra \tall{eierformer.A.kontantstrom.median}~\% for A til
|
||||
\tall{eierformer.C.kontantstrom.median}~\% for C. Tallet er ikke M6 og kan ikke leses som M6. M6 måler det
|
||||
årlige bidraget til Norges inntekt utover vanlig avkastning på kapitalen (\cref{eq:S31}). Statens
|
||||
kontantstrøm er det staten får inn det ene året, etter årets investeringer, uten fradrag for
|
||||
avkastningen på kapitalen som er bundet, og uten de årene da kapitalen ble skutt inn. Nevneren i M6,
|
||||
kontantstrøm er det staten får inn det ene året. For A, B og C er det anleggets første driftsår, og da kjøpes ingen
|
||||
nye brikker: neste årgang betales ved slutten av året før den settes i drift (avklaring~33), og brikkene
|
||||
varer i tre til sju år ($L_H$), så de må kjøpes på nytt hvert tredje til sjuende år. Tallet har ikke
|
||||
fradrag for avkastningen på kapitalen som er bundet, og ikke med de årene da kapitalen ble skutt inn. Nevneren i M6,
|
||||
statens netto kontantstrøm fra petroleum, er samme slags størrelse som statens kontantstrøm i
|
||||
\cref{tab:res-eierformer-kontantstrom}, mens telleren i M6 er bidraget utover vanlig avkastning.
|
||||
Forhåndsregistreringen begrunner telleren: målet skal ikke nås bare ved å være stor («Endringer»,
|
||||
|
|
|
|||
|
|
@ -100,8 +100,8 @@ vurdering.
|
|||
\end{ordrett}
|
||||
|
||||
Raden er altså et avvik fra rundskrivets regel for forretningsdrift i konkurranse, slik vi leser statens
|
||||
regler. Regnemåten betyr at staten bærer risikoen markedet ellers tar betalt for: prisen på regnekraft bygger
|
||||
fortsatt på markedets avkastningskrav, og et lavere krav for alle ville i modellen også gitt lavere pris
|
||||
regler. Statens rente på 4~\% har påslaget for et prosjekt med vanlig risiko \kilde{K09-003}, mens markedets
|
||||
krav for regnekraft er høyere: prisen på regnekraft bygger fortsatt på markedets avkastningskrav, og et lavere krav for alle ville i modellen også gitt lavere pris
|
||||
(\cref{sec:proving}). Raden endrer bare
|
||||
netto nåverdi, det vil si M1 og M7 (avklaring~118~b). \Cref{tab:res-fols-rad16} gir tallene for alle sju
|
||||
løsningene. Med rundskrivets rente får C, R, T-F og T-K positiv netto nåverdi i over 80~\% av trekningene
|
||||
|
|
|
|||
|
|
@ -74,7 +74,8 @@ De raskeste enhetene i modne serier, i Korea og Kina, er bygd på om lag fire ti
|
|||
billigere og raskere enn modellen regner med i de beste utfallene, slik de to funnene over sier at den kan
|
||||
bli dyrere i de dårligste. Runden med fagmiljøene ble gjort etter parameterfrysen. Sammenholdningen
|
||||
prosjekteier fikk før kjøringen, viste bare avvik som kan gjøre kjernekraft dyrere, og bare de to funnene
|
||||
over ble avgjort før kjøringen. Ingen av funnene eller observasjonene er regnet inn. Raden om kostnadsnivået i \cref{tab:fagmiljo}, lagt til 23.~november 2026, viser i
|
||||
over ble avgjort før kjøringen. Ingen av funnene eller observasjonene er regnet inn. Følsomhetslista ble låst før resultatene og har ingen
|
||||
rad med læring over 15~\% per dobling eller med byggekostnad under spennet. Raden om kostnadsnivået i \cref{tab:fagmiljo}, lagt til 23.~november 2026, viser i
|
||||
tillegg tre kostnader under spennet for $c_{N,\text{ref}}$: Olkiluoto~3 med 7\,200 og Saeul~1--2 i Korea
|
||||
med 2\,700~USD/kW (IEA, 2023-dollar, uten renter) \kilde{K28-008}, og Barakah~1--4 i Emiratene, som IEA sier
|
||||
ble ferdig med begrenset overskridelse, med en finansieringsramme på om lag 4\,400~USD/kW, nominelt og med
|
||||
|
|
@ -84,10 +85,11 @@ spennet leses som budsjett (S46). Leses det som sluttkostnad i alle trekningene,
|
|||
kjernekraft på nettet \tall{folsomheter.rad.1.normalisering.B.median} i stedet for
|
||||
\tall{dommer.normalisering.t1.B.nnv-median}~mrd.~kr, og for eget kjernekraftverk
|
||||
\tall{folsomheter.rad.1.normalisering.A.median} i stedet for
|
||||
\tall{dommer.normalisering.t1.A.nnv-median}~mrd.~kr (rad~1 i følsomhetslista). Tre forenklinger i modellen
|
||||
\tall{dommer.normalisering.t1.A.nnv-median}~mrd.~kr (rad~1 i følsomhetslista). Fire forenklinger i modellen
|
||||
trekker på sin side i favør av ny fornybar kraft: magasinene som finnes, jevner ut uten kostnad,
|
||||
vindkraftens verdi faller ikke når mye bygges, og en kald uke uten vind er ikke regnet
|
||||
(\cref{sec:ikke-med-modell}, punkt~1 og~2).
|
||||
vindkraftens verdi faller ikke når mye bygges, en kald uke uten vind er ikke regnet
|
||||
(\cref{sec:ikke-med-modell}, punkt~1 og~2), og vindkraftens inngrep i natur har ingen pris, mens
|
||||
kjernekraftens forventede ulykkeskostnad er regnet med (\cref{sec:ikke-med}).
|
||||
|
||||
% -----------------------------------------------------------------
|
||||
\subsection{Kildene}\label{sec:begrensning-kilder}
|
||||
|
|
@ -270,8 +272,11 @@ vindkraftens verdi faller ikke når mye bygges, og en kald uke uten vind er ikke
|
|||
|
||||
Fagfellene som har lest modellspesifikasjonen, er språkmodeller. De leste postene i kildebanken, ikke
|
||||
primærkildene. Funnene er kontrollert av språkmodellen som har laget modellen, ved å lese ligningene og
|
||||
postene. For 123 poster har den også kontrollert de bærende tallene mot primærkilden, for noen i
|
||||
kontrollørens tekstuttrekk av den («Egenkontroll» i posten; \fil{kilder/README.md}). Ingen av kontrollene
|
||||
postene. Hver post i kildebanken er kontrollert mot primærkilden i kontrollrundene, også det av
|
||||
språkmodeller; resultatet står i postens kontrollinje, og to poster lot seg ikke bekrefte og bærer ingen
|
||||
parameter (\fil{kilder/README.md}). For 123 poster har språkmodellen som laget modellen i tillegg
|
||||
kontrollert de bærende tallene mot primærkilden, en ekstra kontroll, for noen i kontrollørens tekstuttrekk
|
||||
av den («Egenkontroll» i posten). Ingen av kontrollene
|
||||
er gjort av fagpersoner. «Uavhengig» betyr i prosjektet at leseren ikke så prosjektets kode, og i
|
||||
leserundene av rapporten at leseren ikke kjente prosjektets egne konklusjoner om tekstene (fagfelleloggen
|
||||
del~4 og~28). Det betyr ikke en annen språkmodell. Alle leserne er språkmodeller; fagfelleloggen oppgir
|
||||
|
|
|
|||
|
|
@ -40,20 +40,21 @@
|
|||
\begin{tcolorbox}[enhanced,colback=boxbg,colframe=accent,boxrule=0.6pt,arc=1.5pt,left=7pt,right=7pt,top=4pt,bottom=4pt]
|
||||
\textbf{Svaret er nei: hypotesen holder ikke.} Et statlig eid AI-datasenter som selger regnekraft til
|
||||
utlandet, gir tap for Norge når dagens knapphet på regnekraft går over i et normalt marked. Det gjelder alle
|
||||
de fem måtene å skaffe strøm på som er prøvd. Tapet er størst med eget kjernekraftverk, et kraftverk uten
|
||||
nettforbindelse bygd av mange små reaktorer; kjernekraft på nettet taper mindre, og ny fornybar kraft minst.
|
||||
Satsingen blir heller ikke stor nok til å bli en ny olje. Regnekraft som statlig eksportnæring i stor skala
|
||||
bør derfor ikke stå som mål i den nasjonale KI-strategien; rådet bygger på et normalt marked.
|
||||
de fem måtene å skaffe strøm på som er prøvd. Tapet er stort med kjernekraft, størst med eget
|
||||
kjernekraftverk, et kraftverk uten nettforbindelse bygd av mange små reaktorer, og mindre med kjernekraft på nettet. Med ny fornybar kraft er det lite: anlegget går i null i medianen hvis prisen på
|
||||
regnekraft er \tall{terskler.pris.C.normalisering.pst-over}~\% høyere. Satsingen blir heller ikke stor nok
|
||||
til å bli en ny olje. Regnekraft som statlig eksportnæring i stor skala bør derfor ikke stå som mål i den
|
||||
nasjonale KI-strategien; rådet bygger på et normalt marked og på markedets avkastningskrav.
|
||||
\end{tcolorbox}
|
||||
|
||||
\section{Spørsmålet}
|
||||
Tokenfabrikker er AI-datasentre som i prinsippet eies av staten og eksporterer ferdig prosessert regnekraft.
|
||||
Hypotesen var at «statlig eide tokenfabrikker i stor skala lønner seg for Norge og oppfyller vilkårene for
|
||||
strøm og miljø, med den beste av kraftløsningene». Prøven er ærlig ment: svaret kunne blitt ja, nei eller
|
||||
«bare på visse vilkår». Målene og grensene for svaret (lønnsomhet for samfunnet og for virksomheten,
|
||||
strømpris, forsyningssikkerhet, miljø og skala mot petroleumsinntektene) ble godkjent før modellen ble
|
||||
regnet. De ligger i prosjektets åpne git-historikk, ikke i et offentlig register, og presiseringene av dem
|
||||
ble skrevet etter grove overslag fra prosjektets fagfeller, som er språkmodeller.
|
||||
strøm og miljø, med den beste av kraftløsningene». Prøven er ærlig ment: svaret kunne blitt nei eller
|
||||
«bare på visse vilkår». Et fullt ja var i praksis utenfor rekkevidde, for skalagrensen kunne ikke nås (under). Målene
|
||||
og grensene ble godkjent før modellen ble regnet. Presiseringene av dem og endringen av hypotesen kom også
|
||||
før, men etter grove overslag fra språkmodeller; endringen rørte ikke målene og
|
||||
tersklene. Alt ligger i åpen git-historikk, ikke i et offentlig register.
|
||||
|
||||
\section{Hva vi fant}
|
||||
Modellen har 137 parametere, hver med kilde eller merket som åpen forutsetning, og er regnet
|
||||
|
|
@ -69,8 +70,7 @@ over levetiden, regnet om til verdien i dag. For ett anlegg på 1\,000~MW er med
|
|||
\tall{dommer.normalisering.t1.B.nnv-median}~mrd.~kr med kjernekraft på nettet og
|
||||
\tall{dommer.normalisering.t1.A.nnv-median}~mrd.~kr med eget kjernekraftverk. I et normalt marked er prisen
|
||||
på regnekraft satt lik kostnaden til en ny konkurrent med vanlig avkastning, og kraften er om lag 7~\% av
|
||||
den kostnaden. Gevinsten er dermed begrenset av måten prisen er satt på, mens tapet er et funn: med ny
|
||||
fornybar kraft går anlegget i null hvis prisen er \tall{terskler.pris.C.normalisering.pst-over}~\% høyere.
|
||||
den kostnaden. Gevinsten er dermed begrenset av måten prisen er satt på, mens tapet er et funn.
|
||||
Nåverdien er positiv i høyst \tall{dommer.normalisering.t1.C.m1.andel}~\%, men andelen sier ikke hvor
|
||||
sannsynlig en høyere pris er.
|
||||
|
||||
|
|
@ -78,14 +78,16 @@ sannsynlig en høyere pris er.
|
|||
Grensen satt på forhånd: gir satsingen utover vanlig avkastning på kapitalen mindre enn 5~\% av statens
|
||||
netto kontantstrøm fra petroleum, 26,8~mrd.~kr per år, er den ikke «den nye oljen». Ett anlegg ligger under
|
||||
i \tall{dommer.normalisering.t1.A.m6.andel-ikke}~\% av trekningene med alle fem løsningene. Målt som statens
|
||||
kontantstrøm i første år med stabil drift, samme slags størrelse som oljeinntektene, er det i medianen
|
||||
\tall{eierformer.A.kontantstrom.median} til \tall{eierformer.C.kontantstrom.median}~\% av dem, men uten
|
||||
fradrag for avkastningen på kapitalen; det er ikke målet som ble satt. Fem anlegg lar seg ikke bygge innen
|
||||
kontantstrøm i første år med stabil drift er det i medianen
|
||||
\tall{eierformer.A.kontantstrom.median} til \tall{eierformer.C.kontantstrom.median}~\% av dem, men det er
|
||||
et år uten kjøp av nye brikker, som må kjøpes på nytt hvert tredje til sjuende år, og uten fradrag for
|
||||
avkastningen på kapitalen; det er ikke målet som ble satt. Fem anlegg lar seg ikke bygge innen
|
||||
2100 i \tall{dommer.normalisering.t5.TK.m1.ikke-byggbar} til
|
||||
\tall{dommer.normalisering.t5.TF.m1.ikke-byggbar}~\% av trekningene, etter tre åpne forutsetninger om hvor
|
||||
fort kraft og servere kan komme på plass. I et normalt marked kunne grensen derfor i praksis ikke nås; neiet
|
||||
til hypotesen kommer fra lønnsomheten. Dommene leses av på \tall{dommer.trinn} anlegg, slik regelen satt på
|
||||
forhånd sier, og dommen over hypotesen er den samme i alle de seks scenarioene.
|
||||
forhånd sier, og dommen over hypotesen er den samme i alle de seks scenarioene, men når knappheten varer, av en
|
||||
annen grunn (under).
|
||||
|
||||
\talltilpgf{dommer.normalisering.t1.A.nnv.p10}{\aLo}\talltilpgf{dommer.normalisering.t1.A.nnv.p50}{\aMe}\talltilpgf{dommer.normalisering.t1.A.nnv.p90}{\aHi}%
|
||||
\talltilpgf{dommer.normalisering.t1.B.nnv.p10}{\bLo}\talltilpgf{dommer.normalisering.t1.B.nnv.p50}{\bMe}\talltilpgf{dommer.normalisering.t1.B.nnv.p90}{\bHi}%
|
||||
|
|
@ -112,7 +114,7 @@ forhånd sier, og dommen over hypotesen er den samme i alle de seks scenarioene.
|
|||
\nnvrad{2}{\fLo}{\fMe}{\fHi}{TF}\nnvrad{1}{\kLo}{\kMe}{\kHi}{TK}%
|
||||
\end{axis}
|
||||
\end{tikzpicture}
|
||||
\captionof{figure}{Netto nåverdi for Norge av ett anlegg på 1\,000~MW i normalscenarioet: median (prikk) og
|
||||
\captionof{figure}{Netto nåverdi av ett anlegg på 1\,000~MW i normalscenarioet: median (prikk) og
|
||||
de midterste 80~\% av trekningene (strek). Selv de gode utfallene gir tap. Trinnvis med kjernekraft får
|
||||
nesten aldri kjernekraft med ett anlegg.}
|
||||
\end{center}
|
||||
|
|
@ -127,9 +129,9 @@ Resultatet er ikke at regnekraft aldri kan lønne seg. Tre ting kan snu regnesty
|
|||
\tall{karusell.rad16.C.m1-andel}~\% av trekningene. Kjernekraft på nettet får median
|
||||
\tall{folsomheter.rad.16.normalisering.B.median}~mrd.~kr (positiv i \tall{karusell.rad16.B.m1-andel}~\%),
|
||||
eget kjernekraftverk lavere enn i hovedberegningen, \tall{folsomheter.rad.16.normalisering.A.median}~mrd.~kr,
|
||||
mest fordi tapet i kraftverket, som ligger år fram i tid, blir større i dagens kroner. Staten bærer da
|
||||
risikoen markedet ellers tar betalt for: prisen bygger fortsatt på markedets krav, og et lavere krav også
|
||||
der ville gitt lavere pris. Skalaen er ikke regnet på nytt.
|
||||
mest fordi tapet i kraftverket, som ligger år fram i tid, blir større i dagens kroner. Statens rente har
|
||||
påslaget for et prosjekt med vanlig risiko, mens prisen bygger på markedets høyere krav; et lavere
|
||||
krav der ville gitt lavere pris. Skalaen er ikke regnet på nytt.
|
||||
\item \textbf{Knappheten varer.} Holder dagens knapphetspris seg i ti år etter at det første anlegget er i
|
||||
drift (et konstruert scenario uten kilde), er medianen positiv med ny fornybar kraft
|
||||
(\tall{dommer.knapphet.t1.C.nnv-median}~mrd.~kr, positiv i \tall{dommer.knapphet.t1.C.m1.andel}~\%), men
|
||||
|
|
@ -138,8 +140,7 @@ Resultatet er ikke at regnekraft aldri kan lønne seg. Tre ting kan snu regnesty
|
|||
(\tall{dommer.knapphet.t1.A.nnv-median}~mrd.~kr). Hypotesen holder ikke der heller: vilkårene for et ja
|
||||
lar seg ikke tallfeste med tall fra kildene.
|
||||
\item \textbf{Prisen på regnekraft.} Den avgjør mest, og ingen kilde forutsier den. I normalscenarioet må
|
||||
prisen ligge \tall{terskler.pris.C.normalisering.pst-over}~\% over modellens forløp før et anlegg med ny
|
||||
fornybar kraft går i null i medianen, \tall{terskler.pris.B.normalisering.pst-over}~\% med kjernekraft på
|
||||
prisen ligge \tall{terskler.pris.C.normalisering.pst-over}~\% over modellens forløp for null i medianen med ny fornybar kraft, \tall{terskler.pris.B.normalisering.pst-over}~\% med kjernekraft på
|
||||
nettet og \tall{terskler.pris.A.normalisering.pst-over}~\% med eget kjernekraftverk.
|
||||
\end{itemize}
|
||||
|
||||
|
|
@ -151,20 +152,23 @@ Resultatet er ikke at regnekraft aldri kan lønne seg. Tre ting kan snu regnesty
|
|||
utbygging gir likevel større tap i modellen i et normalt marked, og verdien av å kunne stoppe underveis er
|
||||
ikke regnet.
|
||||
\item \textbf{Kraften først. Eget kjernekraftverk uten nett ga størst tap, kjernekraft på nettet mindre.}
|
||||
Sammenlignet med samme modell og regler er eget kjernekraftverk best i \tall{karusell.m7.t1.A.alene}~\% av
|
||||
Eget kjernekraftverk bygger på en amerikansk studie, som selv fant én stor reaktor med nettet som reserve
|
||||
billigere. Kostnadsspennet for kjernekraft er det konsulentene ga Kjernekraftutvalget, som
|
||||
selv fant kjernekraft ulønnsom i Norge med dagens utsikter. Sammenlignet med samme modell og regler er eget kjernekraftverk best i \tall{karusell.m7.t1.A.alene}~\% av
|
||||
trekningene for ett anlegg, ny fornybar kraft i \tall{karusell.m7.t1.C.alene}~\%. Sammenligningen gir
|
||||
ingen dom, og den beste gir også tap. Med fem anlegg er løsningene med kjernekraft oftere best
|
||||
(\tall{karusell.m7.t5.kjernekraft} mot \tall{karusell.m7.t5.fornybar}~\%), fordi så mye ny fornybar kraft
|
||||
sjelden lar seg bygge, men nåverdien er nesten aldri positiv. Hvor mye ny fornybar kraft og hvor mye
|
||||
kjernekraft som kan settes i drift per år, er åpne forutsetninger uten kilde og svært ulike, og
|
||||
sammenligningen med fem anlegg hviler på dem; det bør utredes før noe annet. Kravet til strømprisen holder i
|
||||
sjelden lar seg bygge, men nåverdien er nesten aldri positiv. Byggetakten for fornybar kraft og kjernekraft er åpne forutsetninger uten kilde som sammenligningen med fem anlegg hviler på; det bør utredes først. Kravet til strømprisen holder i
|
||||
\tall{dommer.normalisering.t1.C.m3.andel}~\% av trekningene med alle fem løsningene, fordi de er bygd med
|
||||
like mye ny kraft som datasenteret bruker, regnet som årspris for landet samlet. Kjøpes kraften fra nettet
|
||||
uten ny kraft, holder kravet bare i \tall{dommer.normalisering.t1.R.m3.andel}~\%, og forsyningssikkerheten
|
||||
svekkes per definisjon i \tall{dommer.normalisering.t1.R.m4.andel-ikke}~\%. Med eget kjernekraftverk holder
|
||||
den per definisjon, fordi verket ikke er koblet til nettet; med ny fornybar kraft, vurdert uten tiltak, i
|
||||
\tall{dommer.normalisering.t1.C.m4.andel}~\%. Miljøkravet holder per definisjon for ny fornybar kraft og på
|
||||
vilkår for kjernekraft, som i én av tre kilder har 12 mot 11~g CO\textsubscript{2} per kWh for vind på land.
|
||||
den per definisjon, uten kobling til nettet; vurdert uten tiltak, holder den med ny fornybar kraft i
|
||||
\tall{dommer.normalisering.t1.C.m4.andel}~\% og med kjernekraft på nettet i
|
||||
\tall{dommer.normalisering.t1.B.m4.andel}~\%, fordi kravet regnes med største nye enhet ute, en hel
|
||||
reaktor på 1\,000~MW. Miljøkravet holder per definisjon for ny fornybar kraft og på
|
||||
vilkår for kjernekraft, som i én av tre kilder ligger 1~g over vind på land (12 mot 11~g
|
||||
CO\textsubscript{2}/kWh), men ikke i de to andre.
|
||||
\item \textbf{Det tar lang tid, og etterspørselen kan flytte.} I moduler på 100~MW er de første i drift i
|
||||
\tall{tidslinje.dom.TF.median-aar} i medianen. Et helt anlegg på 1\,000~MW er i drift i
|
||||
\tall{tidslinje.dom.C.halv-1000-aar} med ny fornybar kraft og i \tall{tidslinje.dom.A.halv-1000-aar} med
|
||||
|
|
@ -172,9 +176,8 @@ Resultatet er ikke at regnekraft aldri kan lønne seg. Tre ting kan snu regnesty
|
|||
tilknytning til nettet. Flytter 80~\% av AI-bruken utenom trening til brukernes egne maskiner (prosjektets eget
|
||||
forløp, uten kilde), faller medianen for den beste løsningen til mellom
|
||||
\tall{dommer.egne-lav.t1.C.nnv-median} og \tall{dommer.egne-hoy.t1.C.nnv-median}~mrd.~kr.
|
||||
\item \textbf{Eierformen redder ikke regnestykket.} Med alle fire statlige eierformer er nåverdien for
|
||||
staten negativ i \tall{karusell.eier.tap-lav} til \tall{karusell.eier.tap-hoy}~\% av trekningene.
|
||||
Om de er forenlige med statsstøttereglene i EØS-avtalen, står åpent: vi fant ingen kilde som vurderer det.
|
||||
\item \textbf{Eierformen redder ikke regnestykket.} Med alle fire eierformer er statens nåverdi negativ i \tall{karusell.eier.tap-lav} til \tall{karusell.eier.tap-hoy}~\% av trekningene.
|
||||
Om de er i tråd med statsstøttereglene i EØS-avtalen, står åpent; vi fant ingen kilde om det.
|
||||
\item \textbf{Tett kunnskapshullene, og regn åpent.} Det mangler åpne tall for inntekt og salgsandel per
|
||||
megawatt regnekraft, for statens avkastningskrav og for kraftverk som forsyner ett datasenter uten nett.
|
||||
Hullene kan utredes nå og koster lite mot investeringene det gjelder. Analyser av store investeringer i
|
||||
|
|
@ -187,25 +190,27 @@ statlig eksport av regnekraft i stor skala fra anlegg som eier både bygg og bri
|
|||
datasentre og ikke utleie av bygg og kraft. Verdien av norsk kontroll over regnekraft for beredskap og
|
||||
suverenitet, annen bruk av KI, og om private eiere ville gjort det bedre, er ikke regnet. 40 av de 137
|
||||
parameterne er åpne forutsetninger. Kildene er kontrollert av språkmodeller, ikke av fagpersoner; 123 av
|
||||
1\,236 poster er kontrollert en ekstra gang, også det av en språkmodell. Resultatene er ikke vurdert av
|
||||
1\,237 poster er kontrollert en ekstra gang, også det av en språkmodell. Resultatene er ikke vurdert av
|
||||
eksterne fagfolk, og resultatfilene er gjenskapt bare på samme maskin.
|
||||
|
||||
Forbeholdene går begge veier. Kjernekraft kan bli dyrere enn i modellen: overskridelsene kan ha en
|
||||
tyngre hale, og tilpasning av et utenlandsk reaktordesign til norsk regelverk er ikke regnet inn. Den kan
|
||||
også bli billigere og raskere: kildene viser mer læring og raskere bygging enn spennene tillater,
|
||||
sluttkostnader under spennet for store reaktorer i Finland og Korea, og i Emiratene, et nytt
|
||||
kjernekraftland, om lag 4\,400~USD/kW med renter og tolv år fra vedtak til første enhet på nettet; andre nye
|
||||
kjernekraftland har brukt lenger tid. I om lag
|
||||
halvparten av trekningene legges en overskridelse oppå kostnadsspennet; leses det som sluttkostnad, blir
|
||||
medianen \tall{folsomheter.rad.1.normalisering.A.median}~mrd.~kr med eget kjernekraftverk og
|
||||
\tall{folsomheter.rad.1.normalisering.B.median}~mrd.~kr med kjernekraft på nettet. Eget kjernekraftverk er
|
||||
regnet med avkastningskravet for regnekraft, som er høyere enn kravet for kraft, og det trekker i dets favør:
|
||||
med kravet for kraft blir medianen \tall{folsomheter.rad.3.normalisering.A.median}~mrd.~kr. Tre forenklinger trekker
|
||||
i favør av ny fornybar kraft: magasinene som finnes, jevner ut uten kostnad (ny lagring bygges ikke),
|
||||
vindkraftens verdi faller ikke når mye bygges, og en kald uke uten vind er ikke regnet. To trekker mot alle
|
||||
løsningene: prisen har ingen renter i datasenterets byggetid, og bare Norge kan rammes av stans i
|
||||
leveransene av brikker. Hva Statnetts funksjonskrav for datasentre på nettet koster, er ikke regnet; det
|
||||
trekker i favør av løsningene på nettet. Alt står i rapportens kapittel 6 til 10.
|
||||
tyngre hale, og tilpasning av et utenlandsk reaktordesign til norske regler er ikke regnet inn. Den kan
|
||||
også bli billigere og raskere: kildene viser mer læring og raskere bygging enn spennene tillater, og
|
||||
sluttkostnader under spennet for store reaktorer i Finland og Korea. Emiratene, et nytt kjernekraftland,
|
||||
hadde en ramme på om lag 4\,400~USD/kW med renter og fikk første enhet på nettet tolv år etter vedtaket;
|
||||
andre nye kjernekraftland har brukt lenger tid. Kildene er uenige om kostnadsspennet er et budsjett eller en
|
||||
sluttkostnad, så i om lag halvparten av trekningene legges en overskridelse oppå; leses det som sluttkostnad
|
||||
i alle, blir medianen \tall{folsomheter.rad.1.normalisering.A.median}~mrd.~kr med eget kjernekraftverk og
|
||||
\tall{folsomheter.rad.1.normalisering.B.median}~mrd.~kr med kjernekraft på nettet, og ingen trekning gir overskudd
|
||||
(\tall{folsomheter.rad.1.normalisering.A.m1-andel} og \tall{folsomheter.rad.1.normalisering.B.m1-andel}~\%). Eget kjernekraftverk er regnet med det høyere
|
||||
avkastningskravet for regnekraft, og det trekker i dets favør (med kravet for kraft:
|
||||
\tall{folsomheter.rad.3.normalisering.A.median}~mrd.~kr). Fire forenklinger trekker
|
||||
i favør av ny fornybar kraft: magasinene jevner ut uten kostnad, vindkraftens verdi faller ikke når mye
|
||||
bygges, en kald uke uten vind er ikke regnet, og vindkraftens inngrep i natur har ingen pris, mens
|
||||
ulykkeskostnaden for kjernekraft er med. To trekker mot alle løsningene: prisen har ingen renter i
|
||||
datasenterets byggetid, og bare Norge kan rammes av stans i brikkeleveransene. Statnetts funksjonskrav for
|
||||
datasentre på nettet har ingen pris, og det trekker i favør av løsningene på nettet. Alt står i rapportens
|
||||
kapittel 6 til 10.
|
||||
|
||||
\begin{tcolorbox}[enhanced,colback=boxbg,colframe=accent,boxrule=0.6pt,arc=1.5pt,left=7pt,right=7pt,top=1pt,bottom=1pt,before skip=3pt,after skip=3pt]
|
||||
\small
|
||||
|
|
|
|||
|
|
@ -5,8 +5,9 @@
|
|||
\paragraph{Svaret}
|
||||
\textbf{Hypotesen holder ikke.} Et statlig eid AI-datasenter som selger regnekraft til utlandet, gir tap for
|
||||
Norge når dagens knapphet på regnekraft går over i et normalt marked. Det gjelder alle de fem måtene å
|
||||
skaffe strøm på som er prøvd. Tapet er størst med eget kjernekraftverk, et kraftverk uten nettforbindelse
|
||||
bygd av mange små reaktorer; kjernekraft på nettet taper mindre, og ny fornybar kraft minst. Satsingen blir
|
||||
skaffe strøm på som er prøvd. Tapet er stort med kjernekraft, størst med eget kjernekraftverk, et kraftverk
|
||||
uten nettforbindelse bygd av mange små reaktorer, og mindre med kjernekraft på nettet. Med ny fornybar kraft er det lite: anlegget går i null i
|
||||
medianen hvis prisen på regnekraft er \tall{terskler.pris.C.normalisering.pst-over}~\% høyere. Satsingen blir
|
||||
heller ikke stor nok til å bli en ny olje.
|
||||
|
||||
\paragraph{Spørsmålet}
|
||||
|
|
@ -20,7 +21,8 @@ presiseringene av kriteriene ble skrevet. Hypotesen ble endret før modellen ble
|
|||
overslagene pekte mot at eget kjernekraftverk taper (\cref{sec:endringen,sec:begrensning-gjennomgang}). Fem
|
||||
kraftløsninger sammenlignes med samme modell og regler: eget kjernekraftverk for hvert datasenter, et
|
||||
kraftverk uten nettforbindelse bygd av mange små reaktorer med reserveenheter, etter oppsettet i en studie
|
||||
fra amerikanske nasjonallaboratorier \kilde{K12-001}; kjernekraft på nettet; ny fornybar kraft fra vind og vann; og trinnvis utbygging i moduler på
|
||||
fra amerikanske nasjonallaboratorier, som selv fant at én stor reaktor med nettet som reserve var billigere
|
||||
\kilde{K12-001}; kjernekraft på nettet; ny fornybar kraft fra vind og vann; og trinnvis utbygging i moduler på
|
||||
100~MW med fornybar kraft eller med kjernekraft når den kan komme (\cref{sec:kraftlosningene}). Modellen bygger
|
||||
ingen ny lagring; fleksibiliteten er vannmagasinene som finnes, fast effekt og utkobling. Mye er
|
||||
usikkert, så modellen er regnet \tall{dommer.antall} ganger, hver gang med nye verdier for alt som er
|
||||
|
|
@ -36,7 +38,9 @@ Lønnsomheten for samfunnet måles som netto nåverdi: alle gevinster minus alle
|
|||
levetiden, regnet om til verdien i dag. For ett anlegg på 1\,000~MW er medianen, verdien halvparten av
|
||||
trekningene ligger under, \tall{dommer.normalisering.t1.C.nnv-median}~mrd.~kr med ny fornybar kraft,
|
||||
\tall{dommer.normalisering.t1.B.nnv-median}~mrd.~kr med kjernekraft på nettet og
|
||||
\tall{dommer.normalisering.t1.A.nnv-median}~mrd.~kr med eget kjernekraftverk. I et normalt marked er prisen
|
||||
\tall{dommer.normalisering.t1.A.nnv-median}~mrd.~kr med eget kjernekraftverk. Kjernekraft på nettet er i
|
||||
modellen nye reaktorer på 1\,000~MW som selger til markedet, så mange at produksjonen i et normalår dekker
|
||||
det datasentrene bruker (\cref{sec:kraftlosningene}). I et normalt marked er prisen
|
||||
på regnekraft i modellen satt lik kostnaden til en ny konkurrent med vanlig avkastning, og kraften er om lag
|
||||
7~\% av den kostnaden \kilde{K08-K03}. Gevinsten er dermed begrenset av måten prisen er satt på, mens tapet
|
||||
er et funn: med ny fornybar kraft går anlegget i null i medianen hvis prisen er
|
||||
|
|
@ -48,7 +52,8 @@ kontantstrøm fra petroleum, 26,8~mrd.~kr per år, og den måles mot bidraget ut
|
|||
kapitalen. Ett anlegg ligger under den i \tall{dommer.normalisering.t1.A.m6.andel-ikke}~\% av trekningene.
|
||||
Målt som statens kontantstrøm i første år med stabil drift, samme slags størrelse som oljeinntektene, er ett
|
||||
anlegg i medianen \tall{eierformer.A.kontantstrom.median} til \tall{eierformer.C.kontantstrom.median}~\% av
|
||||
dem; det tallet trekker ikke fra avkastningen på kapitalen og er ikke målet som ble satt på forhånd
|
||||
dem. Det er et år uten kjøp av nye brikker; brikkene må kjøpes på nytt hvert tredje til sjuende år. Tallet
|
||||
trekker heller ikke fra avkastningen på kapitalen og er ikke målet som ble satt på forhånd
|
||||
(\cref{sec:res-eierformer}). I et normalt marked kunne grensen i praksis ikke nås, fordi prisen er satt lik
|
||||
kostnaden og store programmer ikke rekker å bli bygget; neiet til hypotesen kommer fra lønnsomheten. Et
|
||||
program på fem anlegg lar seg ikke
|
||||
|
|
@ -59,7 +64,9 @@ stor del av verdens produksjon av AI-servere ett program kan få. Dommene leses
|
|||
\tall{dommer.trinn} anlegg fordi regelen som ble satt på forhånd, gir det: ingen løsning når 5~\% av
|
||||
oljeinntektene i minst 80~\% av trekningene uansett antall anlegg, og da leses dommene av på det største
|
||||
programmet der minst én løsning har et år med stabil drift i minst 80~\% av trekningene. Dommen over
|
||||
hypotesen er den samme i alle de seks scenarioene, tre for prisen på regnekraft og tre der etterspørselen faller (\cref{sec:res-dommer}).
|
||||
hypotesen er den samme i alle de seks scenarioene, tre for prisen på regnekraft og tre der etterspørselen faller (\cref{sec:res-dommer}),
|
||||
men når knappheten varer, er grunnen ikke tap: vilkårene for et ja lar seg ikke tallfeste med tall fra
|
||||
kildene (under).
|
||||
|
||||
\paragraph{Hva som kunne endre svaret}
|
||||
Resultatet er ikke at regnekraft aldri kan lønne seg. Hovedberegningen bruker et markedsbasert
|
||||
|
|
@ -76,8 +83,8 @@ tallene). Av samme grunn trekker det i favør av eget kjernekraftverk at hovedbe
|
|||
avkastningskravet for regnekraft, som er høyere enn kravet for kraft; med kravet for kraft blir medianen
|
||||
\tall{folsomheter.rad.3.normalisering.A.median}~mrd.~kr. Da er bare nåverdien regnet om:
|
||||
prisen på regnekraft bygger fortsatt på markedets avkastningskrav, og skalaen er ikke regnet på nytt.
|
||||
Regnemåten betyr at staten bærer risikoen som markedet ellers tar betalt for; et lavere krav også i markedet
|
||||
ville i modellen gitt lavere pris. At statens regel for forretningsdrift i
|
||||
Statens rente på 4~\% har påslaget for et prosjekt med vanlig risiko \kilde{K09-003}, mens markedets krav for
|
||||
regnekraft er høyere; et lavere krav også i markedet ville i modellen gitt lavere pris. At statens regel for forretningsdrift i
|
||||
konkurranse med private gjelder her, er prosjektets tolkning, og avkastningskravet for regnekraft er en åpen
|
||||
forutsetning (\cref{sec:kalkulasjonsrenten}). Varer knappheten i ti år etter at det første anlegget er i drift (et konstruert
|
||||
scenario uten kilde), er medianen positiv med ny fornybar kraft
|
||||
|
|
@ -96,8 +103,10 @@ kjernekraft på nettet og \tall{terskler.pris.A.normalisering.pst-over}~\% med e
|
|||
mer; et statlig engasjement bør i så fall være lite, trinnvis og med avtalt pris før kapitalen bindes. At
|
||||
prisen bør være avtalt, er en vurdering; modellen regner ikke en slik avtale. Trinnvis utbygging gir likevel større tap i
|
||||
modellen i et normalt marked, og verdien av å kunne stoppe underveis er ikke regnet.
|
||||
\item \emph{Kraften først. Eget kjernekraftverk uten nett ga størst tap, kjernekraft på nettet mindre.} Med
|
||||
eget kjernekraftverk er medianen lavest av de fem løsningene, og sammenlignet med samme modell og regler er
|
||||
\item \emph{Kraften først. Eget kjernekraftverk uten nett ga størst tap, kjernekraft på nettet mindre.}
|
||||
Kostnadsspennet for kjernekraft er det konsulentene ga Kjernekraftutvalget \kilde{K16-002}, og utvalget fant
|
||||
selv at kjernekraft ikke er samfunnsøkonomisk lønnsomt i Norge med dagens utsikter til kostnader og
|
||||
markedspriser \kilde{K05-005}. Med eget kjernekraftverk er medianen lavest av de fem løsningene, og sammenlignet med samme modell og regler er
|
||||
det best i \tall{karusell.m7.t1.A.alene}~\% av
|
||||
trekningene, ny fornybar kraft i \tall{karusell.m7.t1.C.alene}~\% (\cref{sec:res-m7}).
|
||||
Sammenligningen gir ingen dom, slik forhåndsregistreringen sier: den viser hvor ofte hver er best, og den
|
||||
|
|
@ -114,10 +123,13 @@ kjernekraft på nettet og \tall{terskler.pris.A.normalisering.pst-over}~\% med e
|
|||
anlegget ligger. Kjøpes kraften fra nettet uten ny kraft, svekkes forsyningssikkerheten per definisjon i
|
||||
\tall{dommer.normalisering.t1.R.m4.andel-ikke}~\% av trekningene: «svekkes» betyr svakere enn uten
|
||||
anlegget, uansett hvor lite. Med eget kjernekraftverk holder den per definisjon, fordi verket ikke er koblet
|
||||
til nettet. De andre løsningene er vurdert uten tiltakene som er betalt, og med ny fornybar kraft holder den
|
||||
i \tall{dommer.normalisering.t1.C.m4.andel}~\%. Miljøkravet holder per definisjon for ny fornybar kraft;
|
||||
for kjernekraft holder det på vilkår, fordi kjernekraften i én av tre kilder ligger over vind på land, 12
|
||||
mot 11~g CO\textsubscript{2} per kWh.
|
||||
til nettet. De andre løsningene er vurdert uten tiltakene som er betalt: med ny fornybar kraft holder den
|
||||
i \tall{dommer.normalisering.t1.C.m4.andel}~\%, med kjernekraft på nettet i
|
||||
\tall{dommer.normalisering.t1.B.m4.andel}~\%. Tallet er lavere med kjernekraft på nettet fordi kravet,
|
||||
slik det ble satt på forhånd, regnes med den største nye enheten ute i den knappeste timen, og den er en
|
||||
hel reaktor på 1\,000~MW; ny fornybar kraft har ingen så store enheter. Miljøkravet holder per definisjon
|
||||
for ny fornybar kraft; for kjernekraft holder det på vilkår, fordi kjernekraften i én av tre kilder ligger
|
||||
1~g over vind på land, 12 mot 11~g CO\textsubscript{2} per kWh; i de to andre ligger den ikke over.
|
||||
\item \emph{Det tar lang tid, og etterspørselen kan flytte.} De første modulene er i drift i
|
||||
\tall{tidslinje.dom.TF.median-aar} i medianen, et helt anlegg i \tall{tidslinje.dom.C.halv-1000-aar} med
|
||||
ny fornybar kraft (\cref{sec:res-tidslinje}). Det første årstallet bygger på en åpen forutsetning om 3 til
|
||||
|
|
@ -149,13 +161,17 @@ kjernekraftens favør: kildene viser mer læring og raskere bygging enn de frosn
|
|||
sluttkostnader for store reaktorer i Finland og Korea under spennet i modellen \kilde{K28-008}. Emiratene, et
|
||||
nytt kjernekraftland, bygde Barakah med en finansieringsramme på om lag 4\,400~USD/kW med renter, nominelt
|
||||
\kilde{K03-011}, og fikk første enhet på nettet om lag tolv år etter vedtaket, under modellens nedre grense
|
||||
på 15 år \kilde{K05-034}; andre nye kjernekraftland har brukt lenger tid. I om lag halvparten av
|
||||
trekningene leses kostnadsspennet for kjernekraft som et budsjett, og en overskridelse legges oppå; leses
|
||||
det som sluttkostnad i alle, blir medianen \tall{folsomheter.rad.1.normalisering.A.median}~mrd.~kr med eget
|
||||
kjernekraftverk og \tall{folsomheter.rad.1.normalisering.B.median}~mrd.~kr med kjernekraft på nettet.
|
||||
Observasjonene i kildene er ikke regnet inn. Tre forenklinger trekker i favør av ny fornybar kraft:
|
||||
vannmagasinene jevner ut uten kostnad, verdien av vindkraft faller ikke når mye bygges, og en kald uke uten
|
||||
vind er ikke regnet. To trekker mot satsingen med alle løsningene: prisen på regnekraft har ingen renter i
|
||||
på 15 år \kilde{K05-034}; andre nye kjernekraftland har brukt lenger tid. Kildene er uenige om
|
||||
kostnadsspennet for kjernekraft er et budsjett eller en sluttkostnad \kilde{K16-004, K16-014}, så i om lag
|
||||
halvparten av trekningene leses det som et budsjett, og en overskridelse legges oppå. Leses det som
|
||||
sluttkostnad i alle trekningene, blir medianen \tall{folsomheter.rad.1.normalisering.A.median}~mrd.~kr med
|
||||
eget kjernekraftverk og \tall{folsomheter.rad.1.normalisering.B.median}~mrd.~kr med kjernekraft på nettet, og
|
||||
nåverdien er positiv i henholdsvis \tall{folsomheter.rad.1.normalisering.A.m1-andel} og
|
||||
\tall{folsomheter.rad.1.normalisering.B.m1-andel}~\% av trekningene.
|
||||
Observasjonene i kildene er ikke regnet inn. Fire forenklinger trekker i favør av ny fornybar kraft:
|
||||
vannmagasinene jevner ut uten kostnad, verdien av vindkraft faller ikke når mye bygges, en kald uke uten
|
||||
vind er ikke regnet, og vindkraftens inngrep i natur har ingen pris, mens kjernekraftens forventede
|
||||
ulykkeskostnad er regnet med. To trekker mot satsingen med alle løsningene: prisen på regnekraft har ingen renter i
|
||||
datasenterets byggetid, mens Norge betaler bygget og de første brikkene før oppstart, og bare Norge kan
|
||||
rammes av stans i leveransene av brikker. Hva Statnetts funksjonskrav for datasentre på nettet koster, er
|
||||
ikke regnet; det trekker i favør av løsningene på nettet. Høyere strømpris regnes som en gevinst for landet
|
||||
|
|
|
|||