docs(rapport): close the gaps from critique round 9c
Six critics and six controllers read the report 2026-11-23 and raised 83 objections; none shows a measured number, an equation or the code to be wrong. This commit writes the missing reservations where the reader meets the number, and says what is not computed. - Summary, two-page summary, chapters 1 and 10, README: what the test did and did not try, what the 1.1 % share rests on, the interest rate, the build pace, and the lesson on a dedicated nuclear plant as what the comparison shows (no verdict, as the pre-registration says). - Chapters 2 to 6: reservations at the numbers (shares are not probabilities, the scenario is a choice, sensitivities one at a time). - Chapters 8 and 9, appendix C: computations the critics asked for that are not made, what "independent" means in the project, that the pre-registration was not in a public register. - Source bank area 28 (10 entries, after the results, feeding no parameter): long leases, the largest compute deals, recent reactor costs; cited in chapters 4, 7 and 8. K09-004 gets its NOU quote. - PDFs rebuilt: report 164 pages, summary 2 pages. Every change was read by a controller and the corrections entered; keys, source entries and quotes were checked again by script. The carousel is not changed in this commit. Co-Authored-By: Claude Fable 5.2 <noreply@anthropic.com>
This commit is contained in:
parent
4bf8f26f4b
commit
fe83f9f194
24 changed files with 544 additions and 109 deletions
|
|
@ -41,38 +41,38 @@
|
|||
\textbf{Svaret er nei: hypotesen holder ikke.} Et statlig eid AI-datasenter som selger regnekraft til
|
||||
utlandet, gir tap for Norge når dagens knapphet på regnekraft går over i et normalt marked. Det gjelder alle
|
||||
de fem måtene å skaffe strøm på som er prøvd, og eget kjernekraftverk er den dyreste. Satsingen blir heller
|
||||
ikke stor nok til å bli en ny olje, og bør derfor ikke stå som mål i den nasjonale KI-strategien.
|
||||
ikke stor nok til å bli en ny olje. Regnekraft som statlig eksportnæring i stor skala bør derfor ikke stå
|
||||
som mål i den nasjonale KI-strategien.
|
||||
\end{tcolorbox}
|
||||
|
||||
\section{Spørsmålet}
|
||||
Vi har prøvd én høy ambisjon: at AI-datasentre som i prinsippet eies av staten, og som eksporterer ferdig
|
||||
prosessert regnekraft, kan bli en inntektskilde for Norge slik oljen har vært. Slike datasentre kaller vi
|
||||
tokenfabrikker. Hypotesen var at «statlig eide tokenfabrikker i stor skala lønner seg for Norge og
|
||||
Vi har prøvd om tokenfabrikker, AI-datasentre som i prinsippet eies av staten og eksporterer
|
||||
ferdig prosessert regnekraft, kan bli en inntektskilde for Norge slik oljen har vært. Hypotesen var at «statlig eide tokenfabrikker i stor skala lønner seg for Norge og
|
||||
oppfyller vilkårene for strøm og miljø, med den beste av kraftløsningene». Prøven er ærlig ment: svaret
|
||||
kunne blitt ja, nei eller «bare på visse vilkår».
|
||||
|
||||
\section{Hva vi fant}
|
||||
Mye er usikkert, fra byggekostnader til prisen på regnekraft. Modellen er derfor regnet
|
||||
\tall{dommer.antall} ganger, hver gang med nye verdier for alt som er usikkert, innenfor spennene, fra
|
||||
kildene der de finnes. Hver slik beregning kalles en trekning. Tallene under er \emph{medianen}, verdien halvparten av
|
||||
\tall{dommer.antall} ganger, hver gang med nye verdier innenfor spennene, fra kildene der de finnes. Hver slik beregning kalles en trekning. Tallene under er \emph{medianen}, verdien halvparten av
|
||||
trekningene ligger under, eller andelen av trekningene. Scenarioet som teller, er
|
||||
\emph{normalscenarioet}: prisen på regnekraft har mistet dagens knapphetspåslag før det første anlegget er
|
||||
i drift.
|
||||
i drift. At det skjer så tidlig, er et valg uten kilde, låst før noe ble regnet.
|
||||
|
||||
\paragraph{Ett anlegg gir tap for samfunnet}
|
||||
Lønnsomheten for samfunnet måles som \emph{netto nåverdi}: alle gevinster minus alle kostnader for Norge
|
||||
over hele levetiden, regnet om til verdien i dag. For ett anlegg på 1\,000~MW er medianen
|
||||
\tall{dommer.normalisering.t1.C.nnv-median}~mrd.~kr med ny fornybar kraft og
|
||||
\tall{dommer.normalisering.t1.A.nnv-median}~mrd.~kr med eget kjernekraftverk. Nåverdien er positiv i høyst
|
||||
\tall{dommer.normalisering.t1.C.m1.andel}~\% av trekningene. Figuren viser alle fem kraftløsningene.
|
||||
\tall{dommer.normalisering.t1.C.m1.andel}~\%, med prisen lik kostnaden til en konkurrent med samme avkastningskrav.
|
||||
|
||||
\paragraph{Satsingen blir ikke en ny olje}
|
||||
Før noe ble regnet, satte vi en grense: gir satsingen mindre enn 5~\% av statens netto kontantstrøm fra
|
||||
petroleum, det vil si 26,8~mrd.~kr per år, er den ikke «den nye oljen». Ett anlegg ligger under grensen i
|
||||
\tall{dommer.normalisering.t1.A.m6.andel-ikke}~\% av trekningene, med alle fem løsningene. Et program på
|
||||
fem anlegg lar seg ikke bygge innen 2100 i \tall{dommer.normalisering.t5.TK.m1.ikke-byggbar} til
|
||||
\tall{dommer.normalisering.t5.TF.m1.ikke-byggbar}~\% av trekningene, avhengig av løsningen. Dommen over
|
||||
hypotesen er den samme i alle de seks scenarioene som er regnet: tre for prisen på regnekraft og tre der etterspørselen
|
||||
\tall{dommer.normalisering.t5.TF.m1.ikke-byggbar}~\% av trekningene, avhengig av løsningen. Det hviler på
|
||||
tre åpne forutsetninger om hvor fort kraft og servere kan komme på plass. Dommen over
|
||||
hypotesen er den samme i alle de seks scenarioene: tre for prisen på regnekraft og tre der etterspørselen
|
||||
faller.
|
||||
|
||||
\talltilpgf{dommer.normalisering.t1.A.nnv.p10}{\aLo}\talltilpgf{dommer.normalisering.t1.A.nnv.p50}{\aMe}\talltilpgf{dommer.normalisering.t1.A.nnv.p90}{\aHi}%
|
||||
|
|
@ -87,7 +87,7 @@ faller.
|
|||
\begin{center}
|
||||
\captionsetup{hypcap=false}
|
||||
\begin{tikzpicture}
|
||||
\begin{axis}[width=112mm, height=38mm, scale only axis,
|
||||
\begin{axis}[width=112mm, height=23mm, scale only axis,
|
||||
xmin=-575, xmax=150, ymin=0.4, ymax=5.6, ytick={1,...,5},
|
||||
yticklabels={Trinnvis med kjernekraft (T-K), Trinnvis med fornybar (T-F), Ny fornybar kraft (C),
|
||||
Kjernekraft på nettet (B), Eget kjernekraftverk (A)},
|
||||
|
|
@ -102,28 +102,28 @@ faller.
|
|||
\end{tikzpicture}
|
||||
\captionof{figure}{Netto nåverdi for Norge av ett anlegg på 1\,000~MW i normalscenarioet. Prikken er
|
||||
medianen, og streken dekker de midterste 80~\% av trekningene (fra 10- til 90-persentilen). Alle strekene
|
||||
ligger til venstre for null: selv de gode utfallene gir tap. Med ny fornybar kraft er tapet minst, med
|
||||
eget kjernekraftverk størst.}
|
||||
ligger til venstre for null: selv de gode utfallene gir tap. Trinnvis med kjernekraft får nesten aldri kjernekraft med ett anlegg.}
|
||||
\end{center}
|
||||
|
||||
\section{Hva som kunne endre svaret}
|
||||
Resultatet er ikke at regnekraft aldri kan lønne seg. Tre ting kan snu regnestykket for ett anlegg, men
|
||||
ingen av dem gjør satsingen til en ny olje i et normalt marked.
|
||||
Resultatet er ikke at regnekraft aldri kan lønne seg. Tre ting kan snu regnestykket for ett anlegg.
|
||||
\begin{itemize}[leftmargin=1.2em]
|
||||
\item \textbf{Statens vanlige rente.} Hovedberegningen krever samme avkastning som private ville krevd,
|
||||
fordi statens egne regler sier det for virksomhet i konkurranse med private (rundskriv R-109/2021). Regnet
|
||||
\item \textbf{Statens vanlige rente.} Hovedberegningen krever samme avkastning som private,
|
||||
etter vår lesning av statens regler for virksomhet i konkurranse med private (rundskriv R-109/2021);
|
||||
kravet for regnekraft er en åpen forutsetning. Regnet
|
||||
med statens vanlige kalkulasjonsrente (4~\%, lavere etter 40 år) blir nåverdien positiv med ny fornybar
|
||||
kraft: median \tall{folsomheter.rad.16.normalisering.C.median}~mrd.~kr, positiv i
|
||||
\tall{folsomheter.rad.16.normalisering.C.m1-andel}~\% av trekningene. Skalaen nås fortsatt ikke.
|
||||
\tall{folsomheter.rad.16.normalisering.C.m1-andel}~\% av trekningene. Prisen på regnekraft bygger da fortsatt
|
||||
på markedets krav, og skalaen er ikke regnet på nytt.
|
||||
\item \textbf{Knappheten varer.} Holder dagens knapphetspris seg i ti år etter at det første anlegget er i drift (et
|
||||
konstruert scenario uten kilde), er medianen positiv med ny fornybar
|
||||
kraft (\tall{dommer.knapphet.t1.C.nnv-median}~mrd.~kr, positiv i
|
||||
\tall{dommer.knapphet.t1.C.m1.andel}~\% av trekningene), men fortsatt negativ med eget kjernekraftverk
|
||||
(\tall{dommer.knapphet.t1.A.nnv-median}~mrd.~kr). Hypotesen holder ikke der heller: vilkårene for et ja
|
||||
lar seg ikke tallfeste med tall fra kildene.
|
||||
\item \textbf{Prisen på regnekraft.} Den avgjør mest, og ingen kilde kan forutsi den. I normalscenarioet må
|
||||
prisen ligge \tall{terskler.pris.C.normalisering.pst-over}~\% over modellens forløp for at et anlegg med
|
||||
ny fornybar kraft skal gå i null i medianen, og \tall{terskler.pris.A.normalisering.pst-over}~\% over med
|
||||
\item \textbf{Prisen på regnekraft.} Den avgjør mest, og ingen kilde forutsier den. I normalscenarioet må
|
||||
prisen ligge \tall{terskler.pris.C.normalisering.pst-over}~\% over modellens forløp før et anlegg med
|
||||
ny fornybar kraft går i null i medianen, og \tall{terskler.pris.A.normalisering.pst-over}~\% med
|
||||
eget kjernekraftverk.
|
||||
\end{itemize}
|
||||
|
||||
|
|
@ -131,21 +131,23 @@ ingen av dem gjør satsingen til en ny olje i et normalt marked.
|
|||
\begin{itemize}[leftmargin=1.2em]
|
||||
\item \textbf{Prisen avgjør, og staten rår ikke over den.} Ikke bind staten til stor skala: ingen av
|
||||
løsningene bærer et program på fem anlegg eller mer. Vurderes et statlig engasjement likevel, bør det være
|
||||
lite, trinnvis og med avtalt pris før kapitalen bindes. Trinnvis utbygging gir likevel større tap i
|
||||
lite, trinnvis og med avtalt pris før kapitalen bindes (en vurdering, ikke regnet i modellen). Trinnvis utbygging gir likevel større tap i
|
||||
modellen i et normalt marked, og verdien av å kunne stoppe underveis er ikke regnet.
|
||||
\item \textbf{Kraften først, og ikke eget kjernekraftverk.} På like vilkår kommer ny fornybar kraft best ut i
|
||||
\tall{dommer.m7.normalisering.t1.C.alene}~\% av trekningene for ett anlegg, eget kjernekraftverk i
|
||||
\tall{dommer.m7.normalisering.t1.A.alene}~\%. Med ny fornybar kraft betyr det mest hvor mye ny kraft som kan
|
||||
\item \textbf{Kraften først. Eget kjernekraftverk ga størst tap.} Medianen er lavest av de fem, og på
|
||||
like vilkår er det best i \tall{dommer.m7.normalisering.t1.A.alene}~\% av trekningene for ett anlegg, ny
|
||||
fornybar kraft i \tall{dommer.m7.normalisering.t1.C.alene}~\%. Sammenligningen gir ingen dom, og den
|
||||
beste gir også tap. Med fem anlegg er løsningene med kjernekraft oftere best
|
||||
(\tall{karusell.m7.t5.kjernekraft} mot \tall{karusell.m7.t5.fornybar}~\%), fordi så mye ny fornybar
|
||||
kraft sjelden lar seg bygge, men nåverdien er nesten aldri positiv. Med ny fornybar kraft betyr det mest hvor mye ny kraft som kan
|
||||
settes i drift per år, et tall ingen kilde gir; det bør utredes før noe annet. Strømmen tåler ett anlegg:
|
||||
prisen øker høyst 5~\% i \tall{dommer.normalisering.t1.C.m3.andel}~\% av trekningene, med alle fem
|
||||
løsningene. Kjøpes kraften fra nettet uten at ny kraft bygges, gjelder det bare i
|
||||
\tall{dommer.normalisering.t1.R.m3.andel}~\%, og forsyningssikkerheten svekkes i
|
||||
\tall{dommer.normalisering.t1.R.m4.andel-ikke}~\%.
|
||||
\item \textbf{Det tar lang tid, og etterspørselen kan flytte.} Bygges anlegget i moduler på 100~MW, er de
|
||||
løsningene, regnet som årspris, ikke time for time. Kjøpes kraften fra nettet uten ny kraft, gjelder det bare i
|
||||
\tall{dommer.normalisering.t1.R.m3.andel}~\%, og forsyningssikkerheten svekkes per definisjon
|
||||
i \tall{dommer.normalisering.t1.R.m4.andel-ikke}~\%.
|
||||
\item \textbf{Det tar lang tid, og etterspørselen kan flytte.} I moduler på 100~MW er de
|
||||
første i drift i \tall{tidslinje.dom.TF.median-aar} i medianen. Et helt anlegg på 1\,000~MW er i drift i
|
||||
\tall{tidslinje.dom.C.halv-1000-aar} med ny fornybar kraft og i \tall{tidslinje.dom.A.halv-1000-aar} med
|
||||
kjernekraft. Flytter 80~\% av AI-bruken utenom trening til brukernes egne maskiner (et forløp som er
|
||||
prosjektets eget og uten kilde), faller medianen for den beste løsningen til mellom \tall{dommer.egne-lav.t1.C.nnv-median} og
|
||||
kjernekraft. Flytter 80~\% av AI-bruken utenom trening til brukernes egne maskiner (prosjektets eget forløp, uten kilde), faller medianen for den beste løsningen til mellom \tall{dommer.egne-lav.t1.C.nnv-median} og
|
||||
\tall{dommer.egne-hoy.t1.C.nnv-median}~mrd.~kr.
|
||||
\item \textbf{Eierformen redder ikke regnestykket.} Med alle fire statlige eierformer er nåverdien for
|
||||
staten negativ i \tall{eierformer.C.direkte.tap} til \tall{eierformer.A.direkte.tap}~\% av trekningene.
|
||||
|
|
@ -153,29 +155,33 @@ ingen av dem gjør satsingen til en ny olje i et normalt marked.
|
|||
\item \textbf{Tett kunnskapshullene, og regn åpent.} De åpne tallene for inntekt per megawatt regnekraft er
|
||||
selskapenes egne og spriker mye, og ingen kilde måler hvor mye av kapasiteten som blir solgt. Staten
|
||||
publiserer ikke avkastningskravene til egne selskaper. Et kraftverk som forsyner ett datasenter uten
|
||||
nettet som støtte, har nesten ikke erfaringsgrunnlag. Hullene kan utredes nå og koster lite mot
|
||||
investeringene det gjelder. Analysene staten bygger store investeringer i regnekraft og kraft på, bør være
|
||||
nett, har nesten ikke erfaringsgrunnlag. Hullene kan utredes nå og koster lite mot
|
||||
investeringene det gjelder. Analysene bak store statlige investeringer i regnekraft og kraft bør være
|
||||
åpne: forutsetninger, kilder og kode, og kriterier satt før det regnes.
|
||||
\end{itemize}
|
||||
|
||||
\section{Slik er det prøvd}
|
||||
Målene og grensene for svaret ble skrevet ned og godkjent før noe ble regnet: lønnsomhet for samfunnet og
|
||||
for virksomheten, strømpris, forsyningssikkerhet, miljø og skala mot petroleumsinntektene. Fem
|
||||
kraftløsninger sammenlignes på like vilkår: eget kjernekraftverk for hvert datasenter, kjernekraft på
|
||||
nettet, ny fornybar kraft med lagring, og trinnvis utbygging i moduler med fornybar kraft eller med
|
||||
kjernekraft når den kan komme. Fire statlige eierformer er regnet for hver. Modellen har 137 parametere; 91
|
||||
for virksomheten, strømpris, forsyningssikkerhet, miljø og skala mot petroleumsinntektene. De fem
|
||||
kraftløsningene i figuren sammenlignes på like vilkår, og fire statlige eierformer er regnet for hver. Modellen har 137 parametere; 91
|
||||
av dem er usikre og trekkes på nytt i hver av de \tall{dommer.antall} trekningene. Hvert tall står i
|
||||
parameterfila med kilde eller merket som åpen forutsetning, og kildene ligger i en åpen kildebank med
|
||||
1\,226 poster. Kilder, modell, kode og resultatfiler ligger åpent.
|
||||
parameterfila med kilde eller merket som åpen forutsetning. Parameterfila, kildebanken med 1\,236 poster,
|
||||
modellen, koden og resultatfilene ligger åpent.
|
||||
|
||||
\section{Hva dette ikke er}
|
||||
Modellen er et regnestykke, ikke en offentlig utredning og ikke en anbefaling om å bygge. 40 av de 137
|
||||
Modellen er et regnestykke, ikke en offentlig utredning og ikke en anbefaling om å bygge. Svaret gjelder
|
||||
statlig eksport av regnekraft i stor skala, ikke private datasentre. Verdien av norsk kontroll over
|
||||
regnekraft for beredskap og suverenitet, annen bruk av KI, og om private eiere ville gjort det bedre, er
|
||||
ikke regnet. 40 av de 137
|
||||
parameterne er åpne forutsetninger, der ingen kilde gir tallet direkte. Kildene er kontrollert av
|
||||
språkmodeller, ikke av fagpersoner; 123 av 1\,226 poster er kontrollert en ekstra gang, også det av en
|
||||
språkmodeller, ikke av fagpersoner; 123 av 1\,236 poster er kontrollert en ekstra gang, også det av en
|
||||
språkmodell. Resultatene er ikke
|
||||
vurdert av eksterne fagfolk. To kjente begrensninger kan gjøre kjernekraft dyrere enn i modellen:
|
||||
kostnadsoverskridelsene kan ha en tyngre hale enn modellen regner med, og tilpasning av et utenlandsk
|
||||
reaktordesign til norsk regelverk er ikke regnet inn. Alt står i kapittel 6 til 9 i rapporten.
|
||||
reaktordesign til norsk regelverk er ikke regnet inn. To observasjoner i de samme kildene trekker motsatt
|
||||
vei, mot raskere bygging og mer læring, og tre forenklinger trekker i favør av ny fornybar kraft: magasinene
|
||||
jevner ut uten kostnad, vindkraftens verdi faller ikke når mye bygges, og en kald uke uten vind er ikke
|
||||
regnet. Alt står i rapportens kapittel 6 til 9.
|
||||
|
||||