Six critics and six controllers read the report 2026-11-23 and raised 83 objections; none shows a measured number, an equation or the code to be wrong. This commit writes the missing reservations where the reader meets the number, and says what is not computed. - Summary, two-page summary, chapters 1 and 10, README: what the test did and did not try, what the 1.1 % share rests on, the interest rate, the build pace, and the lesson on a dedicated nuclear plant as what the comparison shows (no verdict, as the pre-registration says). - Chapters 2 to 6: reservations at the numbers (shares are not probabilities, the scenario is a choice, sensitivities one at a time). - Chapters 8 and 9, appendix C: computations the critics asked for that are not made, what "independent" means in the project, that the pre-registration was not in a public register. - Source bank area 28 (10 entries, after the results, feeding no parameter): long leases, the largest compute deals, recent reactor costs; cited in chapters 4, 7 and 8. K09-004 gets its NOU quote. - PDFs rebuilt: report 164 pages, summary 2 pages. Every change was read by a controller and the corrections entered; keys, source entries and quotes were checked again by script. The carousel is not changed in this commit. Co-Authored-By: Claude Fable 5.2 <noreply@anthropic.com>
424 lines
32 KiB
TeX
424 lines
32 KiB
TeX
% =================================================================
|
|
\section{Usikkerhet: trekningene, scenarioene, følsomhetslista og tersklene}\label{sec:usikkerhet}
|
|
% =================================================================
|
|
|
|
\subsection{Trekningene}\label{sec:trekningene}
|
|
|
|
Modellen regnes over 10\,000 trekninger med fast frø og fast generator. De samme trekningene brukes for
|
|
alle løsninger, eierformer, scenarioer og baner. 91 størrelser trekkes. Hendelser som trekkes per år
|
|
(eksportregelen for brikker), har en egen strøm av tilfeldige tall. Trekningene og strømmen ligger som
|
|
datafiler sammen med koden (\fil{data/trekninger.npy}, \fil{data/aarshendelser.npy}) (spesifikasjonen
|
|
kapittel~11).
|
|
|
|
\paragraph{Fordelingene}
|
|
Hver størrelse som trekkes, har én fordeling, valgt etter en fast regel. Gir kildene en lav, en sentral og
|
|
en høy verdi, brukes en beta-PERT-fordeling: en fordeling mellom lav og høy verdi med toppen i den
|
|
sentrale, her med formparameter~4. Gir kildene bare et spenn, er fordelingen jevn, og jevn i logaritmen
|
|
når spennet går over flere tierpotenser. Jevn er den også for 27 av de 30 åpne forutsetningene. Overskridelser er lognormalfordelte. Av de 91 størrelsene er 39
|
|
PERT-fordelte og 48 jevnt fordelte. Én er jevn i logaritmen: hvor ofte en ulykke med stort utslipp
|
|
inntreffer, $5{,}6\cdot10^{-8}$ til $10^{-4}$ per reaktorår \kilde{K04-038, K04-039, K21-034}. Én er
|
|
lognormal: overskridelsen i referanseklassen for kjernekraft, med median 0,648 og avkortet ved den største
|
|
observerte overskridelsen, 12,8 \kilde{K03-044, K03-045, K16-017}. To følger ikke regelen og har noen få
|
|
faste verdier med vekter:
|
|
levetiden for IT-utstyr, 3 til 7 år med vektene 1, 2, 3, 2 og 1 \kilde{K07-003, K07-006, K07-015,
|
|
K08-042}, og tilgjengeligheten reserveenhetene i A dimensjoneres for, 99, 99,5 eller 99,995~\%
|
|
med lik vekt (åpen forutsetning). Én av de jevne, antallet enheter av designet som er bygd i verden før
|
|
Norges første, trekkes som et helt tall fra 1 til 20 med lik sannsynlighet (åpen forutsetning; avklaring 18
|
|
i spesifikasjonen). Faste
|
|
verdier bruker ingen tilfeldige tall. Av de 91 har 60 kilde, 30 er åpne forutsetninger, og én er et valg av
|
|
oppsett: tallet som avgjør om overskridelsen inntreffer i en trekning (\cref{eq:S46}). Tallene er telt i
|
|
parameterfila.
|
|
|
|
\paragraph{Korrelasjonene}
|
|
Fire par av størrelser trekkes med rangkorrelasjon: overskridelsen for kjernekraft og byggetiden (0,5),
|
|
avkastningskravet for kraft og for regnekraft (0,5), kapasitetsfaktoren for kjernekraft og utfallsraten for
|
|
enheter på 300~MW og mer ($-0{,}5$), og forholdet mellom kraft inn og kraft til IT (PUE) i Norge og hos
|
|
konkurrenten (0,5). Alle fire koeffisientene er åpne forutsetninger. Rangkorrelasjon betyr at det er
|
|
rekkefølgen av verdiene, ikke verdiene selv, som henger sammen. Den lages med en gaussisk kopula: hver
|
|
størrelse får et standardnormalt tall, tallene i et par gjøres korrelerte, gjøres om til jevnt fordelte tall
|
|
mellom 0 og 1 og settes inn i den inverse fordelingsfunksjonen for hver størrelse. Korrelasjonen mellom de
|
|
normalfordelte tallene settes til $2\sin(\pi r/6)$, som gir rangkorrelasjonen $r$ (avklaring 17 i spesifikasjonen). Av de
|
|
fire parene er det bare avkastningskravene der den ene siden, kravet for regnekraft, mangler kilde; det har
|
|
betydning for tersklene (\cref{sec:tersklene}).
|
|
|
|
\paragraph{Avkortingen}
|
|
En avkortet fordeling trekkes med den inverse fordelingsfunksjonen til den avkortede fordelingen, ikke ved
|
|
å trekke på nytt. Slik trekkes overskridelsen for kjernekraft. Kapasitetsfaktoren for kjernekraft settes
|
|
lik $(1-o_p)(1-o_f)$, der $o_p$ er planlagt stans og $o_f$ tvungen utfallsrate for enheter på 300~MW og mer, når den trukne verdien er høyere
|
|
(\cref{eq:S4}); det gjøres i trekningene.
|
|
|
|
\paragraph{Eksportregelen}
|
|
Hver trekning har ett jevnt fordelt tall per kalenderår fra 2028 til 2100, fra en egen strøm med eget frø.
|
|
En eksportregel innføres i et år når tallet er lavere enn den trukne sannsynligheten per år. De samme tallene
|
|
brukes for alle løsninger, baner og følsomheter. Strømmen er ikke en trukket størrelse og har ingen
|
|
Sobol-indeks; følsomheten «ingen eksportregel» viser hva den betyr.
|
|
|
|
\paragraph{Slik gjenskapes trekningene}
|
|
Frøet er 20261111 og generatoren PCG64 i numpy; strømmen for eksportregelen har frøet 20261112
|
|
(parameterfila). Størrelsene trekkes i den rekkefølgen de står i parameterfila, og en sammensatt størrelse
|
|
felt for felt. Tabellen har én rad per trekning og én kolonne per størrelse, i parameterfilas enheter. Ved
|
|
siden av ligger en beskrivelse (\fil{data/trekninger.json} og \fil{data/aarshendelser.json}) med navn og
|
|
enhet for hver kolonne (for strømmen: årene), oppsettet, versjonen av numpy (og av scipy for trekningene) og
|
|
sjekksummene for tabellen og parameterfila. Kommandoen
|
|
\begin{center}\small\texttt{PYTHONPATH=src .venv/bin/python -m tokenfabrikker.trekninger kontroll}\end{center}
|
|
lager trekningene på nytt fra parameterfila og sammenligner dem med de lagrede. Den skal skrive
|
|
«identisk», eller «innenfor toleranse» (relativt $10^{-12}$) på en annen maskin; samme kommando med
|
|
\fil{tokenfabrikker.hendelser} kontrollerer strømmen. Alle senere beregninger leser de lagrede filene og lager
|
|
ingen nye trekninger.
|
|
|
|
\paragraph{Hva andelene sier}
|
|
Mange av resultatene oppgis som andeler av trekningene. En slik andel er ikke en sannsynlighet for hva som
|
|
vil skje: den gjelder spennene og fordelingene i parameterfila, fra kildene der de finnes og ellers satt av
|
|
prosjektet, og er ikke bedre enn dem. Der rapporten, som forhåndsregistreringen, kaller et resultat en
|
|
sannsynlighet, som i «sannsynlighet for tap», er det en slik andel. Prisforløpet for regnekraft trekkes ikke,
|
|
men legges inn som scenarioer (\cref{sec:scenarioene}); innenfor et scenario følger prisen av trukne
|
|
størrelser, som konkurrentens kostnad. Hver andel gjelder derfor ett scenario. Trekningene prøver
|
|
usikkerheten i tallene, ikke i oppbygningen av modellen, for eksempel regelen for prisen på regnekraft
|
|
(\cref{eq:S18}). Hvor mye valget av fordelinger betyr, og hva det betyr at alle størrelser utenom de fire
|
|
parene trekkes uavhengig av hverandre, er ikke regnet; ingen linje i følsomhetslista prøver andre
|
|
fordelingstyper eller korrelasjoner.
|
|
|
|
% -----------------------------------------------------------------
|
|
\subsection{Scenarioene}\label{sec:scenarioene}
|
|
|
|
Hovedkjøringen regner seks scenarioer: de tre prisscenarioene «knapphet varer», «normalisering» og
|
|
«overkapasitet», og tre merkede scenarioer for AI-bruk på brukernes egne maskiner, regnet i
|
|
«normalisering»: «kildenes lave forløp» (bortfall 11,9~\% i 2030 og 21,0~\% fra 2035) \kilde{K25-033}, og
|
|
«80~\% på egne maskiner», som er prosjekteiers scenario og ikke har kilde, regnet med trening som 53~\% og
|
|
som 20~\% av AI-lasten, som gir bortfall på 37,6 og 64,0~\% (presisering~14). Dommen som teller, er
|
|
dommen i «normalisering» uten bortfall.
|
|
|
|
Utbyggingen er den samme i alle seks, fordi verken prisen eller bortfallet inngår i den (avklaring 95).
|
|
Scenarioene får ingen sannsynligheter og vektes ikke. Trinnet dommene leses av på, bestemmes én gang, fra
|
|
M6 i «normalisering»; de fem andre scenarioene leses av på samme trinn og vises ved siden av (avklaring 97).
|
|
Står det at skalaen ikke nås, gjelder det derfor hovedforløpet, ikke scenarioet. \Cref{tab:scenarioer}
|
|
viser de seks.
|
|
|
|
{\small
|
|
\setlength{\tabcolsep}{4pt}
|
|
\renewcommand{\arraystretch}{1.15}
|
|
\begin{xltabular}{\linewidth}{@{}P{34mm}>{\hsize=1.15\hsize\raggedright\arraybackslash}X%
|
|
>{\hsize=0.6\hsize\raggedright\arraybackslash}X>{\hsize=1.25\hsize\raggedright\arraybackslash}X@{}}
|
|
\caption{De seks scenarioene i hovedkjøringen. Bortfallet er andelen av etterspørselen etter regnekraft i
|
|
datasentre som faller bort, i 2030 og fra 2035.}\label{tab:scenarioer}\\
|
|
\toprule
|
|
Scenario & Knapphetspåslag & Bortfall & Grunnlag og status \\
|
|
\midrule
|
|
\endfirsthead
|
|
\toprule
|
|
Scenario & Knapphetspåslag & Bortfall & Grunnlag og status \\
|
|
\midrule
|
|
\endhead
|
|
\bottomrule
|
|
\endfoot
|
|
«Normalisering» & ingen & ingen & Dommen som teller \\
|
|
«Knapphet varer» & dagens påslag i ti år fra løsningens første anlegg & ingen & Konstruert; vises ved
|
|
siden av \\
|
|
«Overkapasitet» & prisen 25--45~\% under kostnaden i ti år fra løsningens første anlegg & ingen &
|
|
Konstruert; vises ved siden av \\
|
|
«Kildenes lave forløp» & ingen & 11,9 og 21,0~\% & IEAs laveste forløp for datasentrenes kraftbruk
|
|
\kilde{K25-033}; LBNLs laveste for USA ligger 19,6~\% under i 2030 \kilde{K25-034}; merket \\
|
|
«80~\% på egne maskiner», lav & ingen & 18,8 og 37,6~\% & Prosjekteiers scenario uten kilde; trening 53~\%
|
|
av AI-lasten \kilde{K25-K01}; merket \\
|
|
«80~\% på egne maskiner», høy & ingen & 32,0 og 64,0~\% & Som over, med trening 20~\% av AI-lasten
|
|
\kilde{K25-005}; merket \\
|
|
\end{xltabular}
|
|
}
|
|
|
|
\paragraph{Knapphetspåslaget}
|
|
Prisen på regnekraft er i hovedkjøringen kostnaden hos den som bygger neste anlegg et annet sted
|
|
(konkurrenten, låst til USA), pluss et knapphetspåslag som følger prisscenarioet (\cref{eq:S18}). Dagens
|
|
påslag regnes i hver trekning fra prisen i femårskontrakter fra 2025 og 2026, 101--229~mill.\ kr per MW IT
|
|
og år (9,7--22~mill.\ USD) \kilde{K08-033, K13-005, K13-006}: prisen delt på konkurrentens årskostnad for
|
|
årgang 2025, minus én. Blir påslaget negativt, settes det til null (\cref{eq:S43}). I «knapphet varer»
|
|
står dagens påslag ved lag for årganger som settes i drift før det har gått ti år fra løsningens første
|
|
anlegg; deretter er det null. I «overkapasitet» ligger prisen 25--45~\% under kostnaden for de samme
|
|
årgangene (åpen forutsetning; størrelsen er hentet fra observerte prisfall \kilde{K08-030, K13-012}). I
|
|
«normalisering» er påslaget null for alle årganger: det er borte før første anlegg er i drift.
|
|
|
|
Påslaget avtar altså ikke gradvis i scenarioene. Det står i ti år og faller så bort. Varigheten på ti år
|
|
er et valg (presisering~8), og den er den samme i de to konstruerte scenarioene. Et varig påslag har ingen
|
|
kilde. Den eneste tallfestede analogien kildebanken har, er fra tørrlastfrakt, der etterspørselen etter et sjokk
|
|
er halvert etter om lag to år ifølge kilden (1,4 år regnet fra persistensen den anslår) \kilde{K13-016}. Et varig påslag og et påslag som avtar gradvis, regnes som
|
|
følsomheter (linje 12 og 13 i \cref{tab:folsomheter}). De ti årene regnes fra hver løsnings første anlegg,
|
|
så løsningene møter ulike markeder i «knapphet varer» og «overkapasitet». I T er det første modul, så de ti
|
|
årene kommer tidlig og gjelder få MW. Dommen som teller, berøres ikke.
|
|
|
|
\paragraph{AI-bruk på brukernes egne maskiner}
|
|
Ingen kilde måler eller framskriver hvor stor del av AI-bruken som skjer på brukernes egne maskiner
|
|
\kilde{K25-001, K25-002}. Modellen har ingen etterspørselskurve, så lavere etterspørsel etter regnekraft i
|
|
datasentre virker bare gjennom inntekten per MW. Andelen solgt kapasitet ganges med
|
|
$\mu_d(t_v) = \max(0,\ 1 - \varepsilon_d\, d(t_v))$, der $d(t_v)$ er bortfallet for årgangen $t_v$
|
|
(\cref{eq:S51}). Faktoren står overalt der prisen på regnekraft står, også i M2. Hvor mye inntekten faller
|
|
når etterspørselen faller, har ingen kilde. $\varepsilon_d = 1$ i scenarioene er en åpen forutsetning: inntekten
|
|
faller i takt med etterspørselen. 0,5 og 2 vises som følsomheter (linje 31). Kostnadene er uendret:
|
|
programmet bygges og drives som i banen, og kapasitet som ikke selges, bruker likevel kraft. Kontraktene har
|
|
fast pris gjennom årgangens levetid, så faktoren følger årgangen. Bortfallet går lineært fra null i 2025 til
|
|
verdien for 2030, videre til verdien for 2035, og er fast etterpå.
|
|
|
|
IEAs lave forløp gjelder alle datasentre og skyldes ikke flytting til egne maskiner \kilde{K25-033}; det er
|
|
det nærmeste kildene har. Kildene er uenige om hvor stor del av AI-lasten som er trening, 20--53~\%
|
|
\kilde{K25-005, K25-006, K25-K01}, så scenarioet «80~\%» regnes i begge ender. At flyttingen er fullført i
|
|
2035 og halvveis i 2030, er konstruert; ingen kilde har et forløp. Begge scenarioene er merket der de vises.
|
|
|
|
% -----------------------------------------------------------------
|
|
\subsection{Følsomhetslista}\label{sec:folsomhetslista}
|
|
|
|
Følsomhetslista er låst i parameterfila og vises i én fast tabell med samme format for alle. Ingen dom i
|
|
en følsomhet teller, og sammendraget og konklusjonen i rapporten inneholder bare hovedkjøringens dommer.
|
|
Lista har 37 linjer, som gir 42 rader i kjøringen (avklaring 116 til 125, godkjent av prosjekteier
|
|
13.~november 2026). Ett valg kan trekke i favør av løsning A og står ved raden: raden for inntekt etter
|
|
standardvilkår følger lista, så anlegget får full inntekt når tilgjengeligheten når kravet.
|
|
|
|
\paragraph{Slik regnes en rad}
|
|
En rad er hovedkjøringen med én endring, over de samme trekningene. Linje 11, 17, 19, 31 og 32 har to verdier
|
|
hver og gir to rader. En verdi som byttes, settes inn etter trekningen: de andre størrelsene beholder sine
|
|
trukne verdier, også de den er korrelert med. Åtte av de 37 linjene sa for lite til å regnes uten valg (forhåndsregistreringen,
|
|
«Endringer», 13.~november 2026); der
|
|
er lesningen valgt som endrer minst ut over det linja nevner, slik at raden viser virkningen av den ene
|
|
tingen. Raden leses av på trinnet hovedkjøringens dommer leses av på, med samme grunnlag for trinnet, i
|
|
«normalisering» på hovedforløpet. Trinnet velges ikke på nytt, fordi et eget trinn per rad ville
|
|
sammenlignet programmer av ulik størrelse; M6 på trinnet står i tabellen, så det synes når trinnet ville
|
|
blitt et annet. Unntakene er radene for påslaget, som leses av i «knapphet varer», radene for
|
|
$\varepsilon_d$, som leses av i de tre merkede scenarioene, og de fire radene som bare gjelder eierformene,
|
|
som leses av i tabellene for eierformene (avklaring 112 og 116).
|
|
|
|
En løsning raden ikke gjelder, regnes ikke på nytt og har hovedkjøringens utfall. Dommene per mål settes fra
|
|
radens utfall slik som i hovedkjøringen; M5 er hovedkjøringens. Sammenligningen av kraftløsningene (M7) og
|
|
dommen over hypotesen settes fra radens utfall for de fem løsningene, uten terskler, så langt dommen følger
|
|
av målene. Har hovedkjøringen ikke noe trinn, har lista ingen tabell. Tersklene, Sobol-indeksene, flatene og
|
|
pristerskelen regnes ikke for radene; unntaket er terskelen for bortfall i linje 31.
|
|
|
|
\Cref{tab:folsomheter} viser hva hver rad endrer, hvilke løsninger den gjelder, og hvor den leses av. «Alle»
|
|
er de sju løsningene A, B, $B'$, C, R, T-F og T-K; «de fem» er A, B, C, T-F og T-K. Under «Leses av» står
|
|
«norm.» for «normalisering» på hovedforløpet, «knapphet» for «knapphet varer», «egne maskiner» for de tre
|
|
merkede scenarioene og «eierformer» for tabellene for eierformene.
|
|
|
|
{\footnotesize
|
|
\setlength{\tabcolsep}{3pt}
|
|
\renewcommand{\arraystretch}{1.12}
|
|
\begin{xltabular}{\linewidth}{@{}P{6mm}>{\hsize=1.3\hsize\raggedright\arraybackslash}XP{17mm}P{15mm}%
|
|
>{\hsize=0.7\hsize\raggedright\arraybackslash}X@{}}
|
|
\caption{Følsomhetslista, rad for rad. Nummeret er linjas plass i lista i parameterfila; a og b er to verdier
|
|
på samme linje. Endringen er lesningen i avklaring 117 til 122 i spesifikasjonen. Merknaden ved rad 10 er
|
|
den koden skriver (avklaring 125); de andre bygger på avklaringen som gjelder raden, og ved rad 1 og 2 på
|
|
parameterfila.}\label{tab:folsomheter}\\
|
|
\toprule
|
|
Rad & Hva raden endrer & Gjelder & Leses av & Merknad \\
|
|
\midrule
|
|
\endfirsthead
|
|
\toprule
|
|
Rad & Hva raden endrer & Gjelder & Leses av & Merknad \\
|
|
\midrule
|
|
\endhead
|
|
\bottomrule
|
|
\endfoot
|
|
1 & Kostnadsspennet for kjernekraft er sluttkostnader: ingen overskridelse i noen trekning ($w_\xi = 0$, S46)
|
|
& A, B, $B'$, T-K & norm. & Kildene er uenige om hvilken lesning som gjelder; hovedkjøringen trekker
|
|
$w_\xi$ jevnt mellom 0 og 1 (åpen forutsetning) \\
|
|
2 & Kostnadsspennet er et budsjett: overskridelsen inntreffer i alle trekninger ($w_\xi = 1$)
|
|
& A, B, $B'$, T-K & norm. & Som rad 1 \\
|
|
3 & Avkastningskravet for kraftverket i A lik trekningens krav for kraft som selges i markedet, alle steder
|
|
kravet for A står & A & norm. & \\
|
|
4 & Kravet for kjernekraftverk på nettet 2 prosentpoeng høyere enn for annen kraft, der renten gjelder
|
|
kjernekraftverket selv & B, $B'$, T-K & norm. & A er uendret \\
|
|
5 & Skalaeksponenten for investering $\nu = 0{,}6$ i alle trekninger & A, $B'$ & norm. & I B og T-K har
|
|
enhetene referansestørrelsen \\
|
|
6 & Læringsraten $\ell = -0{,}23$ i alle trekninger & A, B, $B'$, T-K & norm. & \\
|
|
7 & Minstelasten i S7 er 20~\% av merkeeffekten i stedet for snittlasten & A, $B'$ & norm. & Gir mindre
|
|
enheter \\
|
|
8 & Fritt valg av enhetsstørrelse: den som gir lavest kraftkostnad, med en buffer som dekker tapet av største
|
|
enhet & A, $B'$ & norm. & Valget ser ikke inntektsfaktoren, så lavere kostnad per MWh kan gi lavere netto
|
|
nåverdi \\
|
|
9 & Halv byggetid for enheter under 300~MW & A, $B'$ & norm. & B og T-K har store enheter \\
|
|
10 & Inntektsfaktoren er trinnet i standardvilkårene for skyregnekraft \kilde{K15-023} i stedet for S44:
|
|
1 når tilgjengeligheten når kravet, 0,9 når den er minst 99~\%, 0,7 når den er minst 95~\% og 0 under det & A & norm. & Vilkårene erstatter regelen i
|
|
hovedkjøringen: anlegget får full inntekt når tilgjengeligheten når kravet. Raden kan derfor trekke i
|
|
favør av A \\
|
|
11a & Norges andel solgt kapasitet mot konkurrentens 0,90 & alle & norm. & \\
|
|
11b & Samme andel 0,95 & alle & norm. & \\
|
|
12 & Varig knapphet: dagens påslag for alle årganger & alle & knapphet & Hovedkjøringens tall fra samme
|
|
scenario \\
|
|
13 & Avtakende knapphet: påslaget avtar med tiden, $\pi_0 e^{-(t_v-2026)/\tau_\pi}$, med $\tau_\pi$ trukket
|
|
2,0--2,8 år \kilde{K13-016} & alle & knapphet & Som rad 12 \\
|
|
14 & Konkurrentens kraftpris lik EU-snittet for de største kundene, 1\,198~kr/MWh \kilde{K02-044} & alle &
|
|
norm. & \\
|
|
15 & PUE hos konkurrenten 1,45; PUE i Norge beholder sin trekning & alle & norm. & \\
|
|
16 & Rundskrivets rente: 4~\% i år 1--40, 3~\% i år 41--75 og 2~\% deretter, for alle kontantstrømmene i
|
|
netto nåverdi & alle & norm. & Avvik fra rundskrivet. Endrer bare netto nåverdi (M1 og M7) \\
|
|
17a & Skattekostnaden lik null & alle & norm. & \\
|
|
17b & Skattekostnaden 0,20 på all innskutt kapital (nåverdien av alle investeringene) i stedet for på
|
|
subsidieelementet & alle & norm. & \\
|
|
18 & Subsidieelementet regnet med statens lånerente & alle & norm. & \\
|
|
19a & Karbonprisens lave bane i stedet for den sentrale \kilde{K09-013, K09-014} & alle & norm. & \\
|
|
19b & Karbonprisens høye bane & alle & norm. & \\
|
|
20 & Ulykkeskostnaden uten skalering etter enhetsstørrelse (S6) & A, $B'$ & norm. & I B og T-K er
|
|
faktoren 1 \\
|
|
21 & Effektkostnaden (S47) regner bare det største nye enhet er større enn dimensjonerende feil i Norden,
|
|
1\,450~MW \kilde{K17-016} & B, $B'$, T-K & norm. & M4 er uendret. Med enheter på høyst 1\,000~MW faller
|
|
reserveleddet bort \\
|
|
22 & Uten tilleggsregelen (S45): kraftverk på nettet krediteres overskudd & B, $B'$, C, T-F, T-K & norm. &
|
|
Samme tall som vises ved siden av dommene \\
|
|
23 & Ingen eksportregel & alle & norm. & Samme tall som vises ved siden av dommene \\
|
|
24 & Statens kontantstrøm og samlet overskudd verdsettes med statens lånerente; oppgjøret med de private
|
|
fortsatt med kravet for regnekraft & de fem & eierformer & Former med private eiere kommer dårligere ut av
|
|
seg selv: staten antas da å verdsette en usikker kontantstrøm høyere enn markedet \\
|
|
25 & Oppgjøret med de private eierne priset med deres egenkapitalkrav på kontantstrømmen med gjeld & de fem &
|
|
eierformer & Forskjellen i verdi er en overføring til de private; rangeringen etter verdi leses ikke her \\
|
|
26 & Beslutningsår 2030; eksportregelen følger kalenderåret & alle & norm. & Nåverdiene er regnet til 2030
|
|
og kan ikke sammenlignes i størrelse med hovedkjøringens \\
|
|
27 & Anlegg på 300~MW IT, i alle sju løsningene (i T tre moduler per anlegg) & alle & norm. & Programmet er
|
|
30~\% av hovedkjøringens på hvert trinn, og M6 faller tilsvarende \\
|
|
28 & For direkte eierskap og heleid selskap ganges investeringene, også $I^{\text{bud}}$ og fornyelser, og
|
|
driften utenom kraftkjøp, elavgift, nettariff, $q_N E$ og effektkostnaden med $1+\epsilon_e$ (avklaring 52),
|
|
$\epsilon_e$ trukket fra $-0{,}05$ til $0{,}10$ (åpen forutsetning; kildene gir retning og at null er mulig,
|
|
ikke tall \kilde{K10-049, K10-050}) & de fem & eierformer & Dommene og netto nåverdi for Norge
|
|
har ikke faktoren \\
|
|
29 & Statens andel av overskridelsene lik statens eierandel & de fem & eierformer & \\
|
|
30 & M6 mot medianen av de ti årene, 330,1~mrd.\ kr i 2025-kroner (272,2~mrd.\ i løpende kroner), i stedet
|
|
for snittet; samme grenser & alle & norm. & Ingen egen kjøring \\
|
|
31a & $\varepsilon_d = 0{,}5$: inntekten faller halvt så mye som etterspørselen & alle & egne maskiner &
|
|
Terskelen for bortfall regnes om fra samme pristerskel \\
|
|
31b & $\varepsilon_d = 2$: inntekten faller dobbelt så mye & alle & egne maskiner & Som rad 31a \\
|
|
32a & Moduler på 50~MW & T-F, T-K & norm. & \\
|
|
32b & Moduler på 200~MW & T-F, T-K & norm. & \\
|
|
33 & Taket i første trinn 650~MW per år, det som er planlagt tilknyttet av andres reservasjoner i 2027
|
|
\kilde{K22-006} & T-F, T-K & norm. & \\
|
|
34 & Full fortrengning i første trinn: hele uttaket til modulene der tar plass fra private og trenger ikke
|
|
nytt nett & T-F, T-K & norm. & \\
|
|
35 & C bygd i moduler på 100~MW: T-F uten første trinn, med første modul tidligst året nytt nett kan være
|
|
på plass & C & norm. & En egen bane på plassen til C; M7 og dommen over hypotesen er hovedkjøringens \\
|
|
36 & T-K uten vilkåret om minst én hel enhet (S49) & T-K & norm. & \\
|
|
37 & Ny fornybar kraft ut over nullalternativet først fra 2031 \kilde{K23-006} & C, T-F, T-K & norm. & \\
|
|
\end{xltabular}
|
|
}
|
|
|
|
\paragraph{Hva datafila og resultatkapitlet viser}
|
|
Fila \fil{data/resultater/folsomheter.json} har for hver rad og løsning andelen trekninger som oppfyller vilkåret for
|
|
«holder» i M1, M2, M3, M4 og M6, og dommen i hvert; medianen av netto nåverdi; andelen trekninger der banen
|
|
ikke lar seg bygge; tallene ved siden av M6 (også M6 mot medianen av de ti årene); sammenligningen av de fem
|
|
løsningene (andelen der hver er best alene, andelen der plassen deles, og andelen der ingen lar seg bygge);
|
|
og ordet for hypotesen på trinnet, uten terskler. Resultatkapitlet viser andelene og medianen rad for rad
|
|
med hovedkjøringens tall fra samme scenario, dommeordene som endres, sammenligningen for hver rad og ordet
|
|
for hypotesen der det endres. En løsning raden ikke gjelder, har hovedkjøringens tall. Tabellene står i
|
|
\cref{sec:res-folsomheter}: \cref{tab:res-fols-rader} rad for rad, \cref{tab:res-fols-m7} for
|
|
sammenligningen av kraftløsningene og \cref{tab:res-fols-del1} for ordet for hypotesen.
|
|
|
|
% -----------------------------------------------------------------
|
|
\subsection{Tersklene, betingelsene og den globale følsomheten}\label{sec:tersklene}
|
|
|
|
Ved siden av dommene regner modellen hvilken pris på regnekraft satsingen tåler, hvilke verdier av de
|
|
usikre størrelsene et mål holder under, og hvilke størrelser som betyr mest for utfallet. Alt regnes fra de
|
|
samme trekningene som dommene; ingen nye trekninger lages (avklaring 105 til 115). Tersklene og indeksene
|
|
gis på trinnet dommene leses av på. Finnes det ikke noe trinn, gis ingen av dem.
|
|
|
|
\paragraph{Pristerskelen}
|
|
Prisen på regnekraft kan ingen kilde forutsi, og dommen skal også uttrykkes som en terskel: hvilken pris
|
|
satsingen tåler (regel~3). Prisen ganges med en faktor $k$ for alle årganger, alle steder prisen står i
|
|
modellen. Påslaget i \cref{eq:S43} regnes som før, og utbyggingen og kostnadene er uendret. For hver løsning
|
|
er $f(k)$ medianen av netto nåverdi over alle trekningene med faktoren $k$; en trekning der banen ikke lar
|
|
seg bygge, rangeres under alle verdier. Netto nåverdi øker ikke når prisen faller, så pristerskelen er den
|
|
minste $k$ som gir median netto nåverdi null eller høyere. Den oppgis med en nøyaktighet på $10^{-6}$. Det søkes opp til
|
|
$k = 100$; ligger terskelen over, står det «over 100». Lar banen seg ikke bygge i minst halvparten av
|
|
trekningene, har medianen ingen verdi, og terskelen finnes ikke, uansett pris. Terskelen gis for de sju
|
|
løsningene i hvert av de tre prisscenarioene (avklaring 105).
|
|
|
|
Terskelen holdes mot kontraktsprisene i kildene, slik spesifikasjonen kapittel~3.2 sier. Den er «innenfor
|
|
spennet i kontraktsprisene» når $k$ ganger medianen over trekningene av konkurrentens årskostnad for årgang
|
|
2025 ikke er høyere enn den høyeste kontraktsprisen, 229~mill.\ kr per MW IT og år
|
|
\kilde{K08-033, K13-005, K13-006}. Ved siden av står andelen trekninger der det holder i trekningen.
|
|
Kontrollen endrer ingen dom (avklaring 106). Den er en øvre grense, fordi den bruker den høyeste
|
|
kontraktsprisen, og gjelder prisen uten påslag: i
|
|
«knapphet varer» er prisen ved terskelen høyere for årgangene med påslag.
|
|
|
|
\paragraph{Terskelen for bortfall av etterspørsel}
|
|
Fordi faktoren for bortfall står alle steder prisen står, er et bortfall $d$ likt for alle årganger det
|
|
samme som å gange prisen med $1 - \varepsilon_d d$. Terskelen for bortfall er derfor pristerskelen uttrykt
|
|
som bortfall: $d^{*} = \min(1, \max(0, (1-k)/\varepsilon_d))$, med pristerskelen $k$ i «normalisering»
|
|
(\cref{eq:S52}). Er $k$ én eller mer, tåler satsingen ikke noe bortfall, og $d^{*} = 0$. $d^{*} = 1$ betyr at
|
|
medianen ikke er negativ selv om hele etterspørselen faller bort, ikke at den er null der. Har $k$ ingen
|
|
verdi, har heller ikke $d^{*}$ det. Med $\varepsilon_d$ lik 0,5 og 2 regnes $d^{*}$ om fra samme $k$
|
|
(avklaring 107). Terskelen hviler på en forutsetning uten kilde og teller aldri som betingelse
|
|
(presisering~14). Den vises sammen med bortfallet i de merkede scenarioene.
|
|
|
|
\paragraph{Tersklene i de trukne størrelsene}
|
|
En terskel gjelder én løsning, ett mål med dommen «holder under betingelser», én trukket størrelse og én
|
|
retning (avklaring 108). Vilkåret i hver trekning er vilkåret for «holder» i målet; en trekning der banen
|
|
ikke lar seg bygge, oppfyller det ikke. Kandidatene er de trukne verdiene av størrelsen som ligger mellom
|
|
10- og 90-persentilen over alle trekningene. Betingelsen «høyst $c$» gjelder trekningene der størrelsen er
|
|
$c$ eller lavere, og «minst $c$» dem der den er $c$ eller høyere. Målet holder under betingelsen når vilkåret
|
|
er oppfylt i minst 80~\% av trekningene betingelsen gjelder. Terskelen er den minst strenge betingelsen
|
|
innenfor spennet: i retningen «høyst» den største kandidaten målet holder under, og i retningen «minst» den
|
|
minste. Den sier ikke at målet holder under hver strengere verdi. Ved siden av hver terskel står
|
|
sannsynligheten for at betingelsen er oppfylt, og andelen som oppfyller vilkåret blant trekningene den
|
|
gjelder.
|
|
|
|
Det søkes blant alle de 91 trukne størrelsene, én om gangen; to størrelser samtidig vises som flater (under).
|
|
Tersklene søkes for M1, M2, M3, M4 og M6, for hver løsning målet er «holder under betingelser» for, i hvert
|
|
scenario. For sammenligningen av kraftløsningene søkes ingen terskel, fordi den ikke har noen dom
|
|
(avklaring 135).
|
|
|
|
\emph{Når en terskel teller som betingelse.} De tre kravene i \cref{sec:samletdom} gjelder. Størrelsen må ha
|
|
kilde (presisering~5). En terskel i en åpen forutsetning rapporteres som «avhenger av en forutsetning uten
|
|
kilde». En terskel i tallet som avgjør om overskridelsen inntreffer, vises som «trekninger med (eller uten)
|
|
overskridelse»; forutsetningen bak er vekten $w_\xi$. Virkningen må være påvist (presisering~22). Det
|
|
trengs fordi søket går over mange størrelser og mange kandidater: en uavhengig leser målte på oppdiktede tall
|
|
at størrelser uten noen virkning ofte fikk en terskel når andelen lå mellom om lag 77 og 80~\%. Prøven er
|
|
Pearsons kjikvadratprøve for uavhengighet mellom størrelsen, delt i 50 klasser etter verdien, og vilkåret, på
|
|
0,1~\%-nivå. Med 10\,000 trekninger og 50 klasser må indeksen i avsnittet om Sobol-indekser under være større
|
|
enn 0,0085. En terskel som ikke består prøven, vises med «virkning ikke påvist» og teller ikke. Til sist
|
|
teller en terskel i avkastningskravet for kraft bare når målet holder under den samme betingelsen både blant
|
|
trekningene der kravet for regnekraft ligger til og med medianen, og blant dem der det ligger over
|
|
(presisering~23). Kravet for regnekraft er en åpen forutsetning og korrelert med kravet for kraft, og en
|
|
terskel i kravet for kraft kunne ellers bære virkningen av det.
|
|
|
|
\emph{Betingelsene for hypotesen} settes fra tersklene etter reglene i \cref{sec:samletdom}: for hvert av M1
|
|
til M4 som er «holder under betingelser», minst én terskel som teller, og for M5 at kildene der
|
|
kjernekraften ikke ligger høyere, legges til grunn (presisering~17). M6 trenger ingen terskel, fordi M6 ikke alene kan felle en
|
|
løsning (presisering~21). For hvert mål skrives
|
|
betingelsene som teller, ut med størrelse, retning, terskel, sannsynlighet og andel, og for seg tersklene i
|
|
størrelser uten kilde. Hvert mål prøves for seg, så en løsning kan få betingelser som ikke kan være oppfylt
|
|
samtidig. Derfor vises det for hver løsning med betingelser hvor stor andel av trekningene som oppfyller
|
|
betingelsene samtidig (for hvert mål den som teller med høyest sannsynlighet), og blant dem andelen der
|
|
vilkårene for «holder» i M1 til M4 alle er oppfylt. Tallene endrer ingen dom (avklaring 115).
|
|
|
|
\paragraph{Terskelflatene}
|
|
Tre flater viser to størrelser samtidig, på trinnet dommene leses av på og i «normalisering» (avklaring 111
|
|
og 134). Trekningene deles i fem om lag like store klasser etter hver størrelse. (a)
|
|
\emph{Pris på regnekraft mot reaktorkostnad:} pristerskelen regnet i hver av de fem klassene av
|
|
investeringen for en stor reaktor, for A, B, $B'$ og T-K. (b) \emph{Kraftpris hos konkurrenten mot
|
|
kostnaden for norsk kraft:} konkurrentens kraftpris mot kraftkostnaden bedriften betaler, nåverdivektet
|
|
over årgangene, for de sju løsningene, over trekningene der banen lar seg bygge. (c)
|
|
\emph{Avkastningskrav mot reaktorkostnad:} kravet for regnekraft og kravet for kraft, hver mot
|
|
reaktorkostnaden, for A, B, $B'$ og T-K. Flatene (b) og (c) har 25 ruter, og for hver rute gis antall trekninger, andelen med positiv netto
|
|
nåverdi og medianen av netto nåverdi; flaten er grensen mellom rutene med positiv og ikke
|
|
positiv median. For hver klasse langs aksene gis antall trekninger og medianen av størrelsen. Flatene (b)
|
|
og (c) er fordelinger i de lagrede trekningene, ikke kjøringer med størrelsene satt til faste verdier, og
|
|
holder seg derfor innenfor spennene i parameterfila; flate (a) regner modellen på nytt med prisfaktoren,
|
|
men på de samme trekningene. Flatene endrer ingen dom.
|
|
|
|
\paragraph{Sobol-indeksene}
|
|
Sobol-indeksen av første orden for en størrelse er den delen av variansen i et utfall som kan føres til
|
|
den størrelsen alene. Den anslås fra de lagrede trekningene uten nye kjøringer (avklaring 110). Trekningene
|
|
deles i $\max(2, \lfloor\sqrt{N}/2\rfloor)$ klasser etter størrelsens verdi, der $N$ er antall trekninger
|
|
som inngår, altså 50 med 10\,000 trekninger, og indeksen er variansen mellom klassesnittene av utfallet,
|
|
vektet med antallet i hver klasse, delt på variansen i utfallet. Anslaget er skjevt oppover: uten noen
|
|
virkning er det om lag antall klasser med trekninger minus én delt på antall trekninger minus én: 0,0049 for
|
|
en kontinuerlig størrelse med 10\,000 trekninger, lavere for en størrelse med få verdier (avklaring 114 g).
|
|
Tallet står ved tabellen, og ingen indeks rettes for det.
|
|
|
|
Indeksen regnes for hver av de 91 trukne størrelsene, også vekten $w_\xi$, og for hver av de sju løsningene
|
|
på trinnet dommene leses av på, i «normalisering». Utfallene er: netto nåverdi, blant trekningene der banen
|
|
lar seg bygge; om banen lar seg bygge; vilkåret for «holder» i M1, M2, M3, M4 og M6, og for M3, M4 og M6
|
|
også vilkåret for «holder ikke»; og for hver av de fem løsningene om den er blant de beste i
|
|
sammenligningen, alene eller delt (avklaring 135 og 137). M5 har ingen indeks. Totalindekser, som også tar
|
|
med samspillet med andre størrelser, kan ikke anslås fra gitte trekninger uten en erstatningsmodell og gis
|
|
ikke; én minus summen av førsteordensindeksene viser hvor mye som ikke kan føres til én størrelse alene. For
|
|
de fire korrelerte parene inneholder indeksen for den ene det den deler med den andre. Metoden er kjent som
|
|
anslag fra gitte data (Plischke, Borgonovo og Smith 2013). Prosjektet har ikke lest artikkelen; det som
|
|
gjelder, er formelen i avklaring 110.
|
|
|
|
Resultatene står i \cref{sec:res-terskler}: pristerskelen i \cref{tab:res-pristerskel}, terskelen for
|
|
bortfall i \cref{tab:res-bortfall}, tersklene i de trukne størrelsene i
|
|
\cref{tab:res-terskler-normalisering}, betingelsene i \cref{tab:res-betingelser}, flatene i
|
|
\cref{fig:res-prisflate} og \cref{tab:res-flater}, og Sobol-indeksene i \cref{tab:res-sobol}.
|