ms-ai-architect/playground/test-fixtures/conformity.md
Kjell Tore Guttormsen 2e9bc5e0bb
fix(playground): align the demo project description with its reports
The demo project card now describes the system the 17 demo reports are about: a citizen chatbot that pre-assesses applications for municipal housing allowance (bostøtte) from uploaded attachments. It previously described a building-permit (byggesak) chatbot that no report mentions.

Six fixtures (classify, requirements, conformity, review, adr, summary) are set equal to the corrected text already inlined in the demo block: the Annex III deadline 2027-12-02 and the 2026-08-02 transparency label, instead of 2027-08-02. Chose syncing the fixtures to the block over editing the block by hand, because the block is build output and a rebuild from the old fixtures would have put the wrong deadlines back in the demo.

Rebuilt the demo state and regenerated the 24 screenshots once with tests/screenshot/run.mjs; MANIFEST.json matches the new demo state.

Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
2026-09-23 15:06:19 +02:00

1.7 KiB

Samsvarsvurdering (Art. 43) — Acme Kunde-chatbot

System: Acme Kunde-chatbot (Acme Kommune) Vurderingsprosedyre: Annex VI (intern kontroll)

Sjekkliste

Krav Status Bevis
Risk Management System dokumentert bestått RMS-rapport v2.1 (2026-04-15)
Treningsdata-governance med kvalitetskriterier bestått Data-governance handbook §4.2
Teknisk dokumentasjon Annex IV komplett betinget Mangler ytelsesmål per stratum
Logging av hendelser implementert bestått OpenTelemetry-spans i Azure Monitor
Transparens-instruksjoner skrevet avvist Skal leveres innen 2026-09-01
Menneskelig oversikt på saksbehandler bestått Workflow-design godkjent av juridisk
Nøyaktighetsmål dokumentert betinget 96.3% overall, men ikke per språkgruppe
Robusthet under adversarielle forhold betinget Test-suite mangler skannede, skjeve og håndskrevne vedlegg
Cybersikkerhetstiltak per Art. 15 bestått NSM Grunnprinsipper-vurdering bestått
Conformity assessment underskrevet avvist Avhengig av FRIA-resultat
EU declaration of conformity utstedt avvist Avhenger av Art. 47
CE-merking påført avvist Markedsplassering ikke aktuell (intern bruk) — vurder om Art. 48 gjelder

Frister

Dato Milepæl Status
2026-08-02 Transparens (Art. 50) upcoming
2026-09-01 Transparens-instruksjoner ferdigstilt upcoming
2027-02-01 FRIA og DPIA-revisjon upcoming
2027-12-02 Full Annex III høyrisiko-compliance (utsatt fra 2026-08-02) upcoming

Konklusjon

5 av 12 krav er fullt møtt; 4 er delvis møtt; 3 mangler implementering. Critical path: transparens-instruksjoner (Art. 13) blokkerer conformity declaration.