Commit graph

8 commits

Author SHA1 Message Date
fd0db8b3d3
docs(modell): settle the ambiguities found by the second independent coding
A second independent reader coded the build-out, the power system and the cash
flow (S12, S22-S26, S33-S35, S38-S41, S45 and the sharing of S47) for all five
power solutions from the specification alone. It found 28 ambiguities, and ten
more when it coded again from the clarifications. Clarifications 21-40 in
chapter 16 settle them; clarification 29 (the nuclear units in B) was rewritten
twice after the reader showed that the first two rules were wrong. With the
final text the two implementations agree on 10 000 made-up build-out paths.

The clarifications that are choices are marked and put to the project owner.
Whether chips are counted from the decision year or from the first possible
operating year is left open until the owner has answered. The parameter file
and the pre-registration are unchanged, and no result has been computed.

Co-Authored-By: Claude Fable 5.2 <noreply@anthropic.com>
2026-11-12 11:58:13 +01:00
9c960950ae
docs(modell): record the project owner's approval of three clarifications
Clarifications 5, 10 and 11 in chapter 16 are choices, not only readings.
The project owner approved them on 2026-11-12, before any result, and decided
that the yearly production loss NVE assumes for wind is not added: the
deviation from NVE is to be stated in the report and the freeze stands.

Co-Authored-By: Claude Fable 5.2 <noreply@anthropic.com>
2026-11-12 10:46:33 +01:00
736f636691
docs(modell): settle the ambiguities found by independent coding
An independent reader coded the key equations from the specification alone
and listed 19 ambiguities (4 blocking). Chapter 16 of the specification now
says how the text is to be read, dated 2026-11-12, after the parameter freeze
and before any result. Equations, equation numbers and the parameter file are
unchanged. The review log records each finding, what was done, and the
outcome of the known-answer tests.

Co-Authored-By: Claude Fable 5.2 <noreply@anthropic.com>
2026-11-12 10:08:47 +01:00
28eaa80f09
docs(forhandsregistrering): enter the eight approved clarifications
The project owner approved the eight proposed clarifications of the
pre-registered criteria on 2026-11-12, as recommended, after the
parameter freeze and before any code or result exists. They are entered
under «Presiseringer» with a dated entry and the reason for each under
«Endringer». Three wordings in the criteria text are aligned with them.

The specification now refers to them as clarifications instead of
proposals, and the rule for conditions uses the 10th to 90th percentile.
Equations and parameters are unchanged; modell/parametere.json keeps its
checksum.

Co-Authored-By: Claude Fable 5.2 <noreply@anthropic.com>
2026-11-12 09:07:33 +01:00
01b27fad78
feat(modell): freeze parameters
124 parameters for the model in modell/spesifikasjon.md (draft 3), all
amounts in real 2025 kroner, one distribution per parameter, each with
the source bank entries it rests on. 80 follow from confirmed entries,
1 is derived from them, 35 are open assumptions with a stated range and
8 are set-up choices. The file also fixes the conversion rule, the
Monte Carlo set-up and the list of sensitivities.

Frozen before anything is computed and before any code exists. The file
is not edited after this commit; a change is a deviation with a new
checksum and a dated entry in the pre-registration.

Co-Authored-By: Claude Fable 5.2 <noreply@anthropic.com>
2026-11-12 00:57:57 +01:00
9e3feb367e
docs(modell): add specification draft 3 and review log
Draft 3 has 47 equations. Changes follow the pre-read of draft 2
(44 findings), two independent reviews of draft 3 (55 and 22 findings)
and an independent control of the corrections (39 findings). Each
finding was checked by the project before it was corrected; the log
says what was done with each.

Main changes: all parameters in 2025 kroner; explicit cash flows per
solution; the price of compute set per MW sold, so that unsold capacity
is not charged to Norway alone; power plants on the grid are never
credited a surplus (S45); the reading of the Norwegian nuclear cost
range is drawn (S46); dimensioning, build-out and residual value are
specified. Eight proposed clarifications of the pre-registration are
listed in chapter 15 and are not entered there.

Co-Authored-By: Claude Fable 5.2 <noreply@anthropic.com>
2026-11-12 00:57:41 +01:00
2a9d463690
docs(forhandsregistrering): enter nine approved clarifications
Approved by the project owner after two independent reviews of the
model specification, before anything is computed and before any code
exists: overall verdict, M2 against the price of compute, verdict per
price scenario with fixed build-out paths, the M4 requirement, M3 in
normal and dry years, the M6 numerator and year, a symmetric M7
threshold, a grid-purchase reference run, and the limit for state risk.

Co-Authored-By: Claude Fable 5.2 <noreply@anthropic.com>
2026-11-11 22:26:48 +01:00
5a4d9b0072
docs(modell): add model specification draft 2 and review log
Draft 1 was read by two independent reviewers (a subject reviewer and a
devil's advocate). Draft 2 corrects the equations they found wrong
(levelised price, token cost unit, welfare sign, double counting) and
models off-grid operation with unit size limits and reserve units.
Findings that touch the pre-registered criteria are listed as open
decisions, not applied.

Co-Authored-By: Claude Fable 5.2 <noreply@anthropic.com>
2026-11-11 22:20:04 +01:00